Construction Updates
October 17, 2024- This week, City contractors poured sections of new sidewalk along the east side of 80th Avenue SE at SE 32nd Street. City contractors also patched back asphalt sections that had been removed to install the new curb and gutter. Next week, crews plan to continue pouring new sidewalk between SE 30th and SE 32nd Streets; however, this work is weather dependent.
|
|
|
October 10, 2024- This week, City contractors poured sections of new sidewalk along the east side of 80th Avenue SE at SE 32nd Street. Next week, crews plan to continue pouring new sidewalks between SE 30th and SE 32nd Streets; however, this work is weather dependent. Also next week, crews will be removing two street trees on the east side of 80th Avenue SE just south of SE 28th Street.
October 4, 2024- This week, City contractors poured additional new curb and gutter along the east side of 80th Avenue SE at SE 32nd Street. They also continued with installing electrical conduit for the new illumination system and also started grading for new sidewalks. Later next week, crews hope to begin pouring new sidewalk between SE 30th and SE 32nd Streets.
September 26, 2024- This week, the City’s contractor, Always Active Services, placed crushed rock and graded for curb, gutter and sidewalk along the east side of 80th Avenue SE at SE 32nd Street. They also continued excavation and installation of new electrical conduit for the new illumination system and their subcontractor, Custom Concrete, began pouring new curb and gutter. Next week, crews will continue with grading, conduit installation and curb and gutter between SE 30th and SE 32nd Streets.
September 19, 2024- This week, the City’s contractor, Always Active Services, removed asphalt along the east side of 80th Avenue SE at SE 32nd Street. They also started excavation and installation of new electrical conduit for the new illumination system. Next week, crews will continue removals and conduit installation between SE 30th and SE 32nd Streets. They will also begin placing crushed rock and grading for new curb, gutter and sidewalk.
September 12, 2024 - This week, the City’s contractor, Always Active Services, started removing the old concrete curb, gutter, and sidewalk along the east side of 80th Avenue SE, between SE 30th and SE 32nd Streets. Next week, crews will continue removals and start underground utility work for the new street lighting between SE 30th and SE 32nd Streets. Following the utility work new concrete curb, gutter, and sidewalk will be poured.
|
|
|
|
September 6, 2024 - This week, the City’s contractor, Always Active Services, removed trees along the east side of 80th Avenue SE, between SE 30th and SE 32nd Streets due to large root masses that are heaving the existing sidewalk. The trees being removed will be replaced with new trees this fall/winter after the construction of the new sidewalk is completed. Next week, crews will begin sidewalk removals and underground utility work for the new street lighting between SE 30th and SE 32nd Streets.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends