Construction Updates

January 10, 2025- This week crews resumed work after the holidays and continued grading for new curb, gutter, sidewalk and driveways along the east side of 80th Avenue between SE 27th and SE 28th Streets and were also able to pour concrete in some of those areas. The electrical subcontractor poured the final new light pole bases and a mounting pad for the new lighting control cabinet. Sidewalk areas were also poured this week at the nearby Sound Transit traffic signal improvement project at the SE 27th Street and 80th Avenue intersection. Next week crews will continue working between SE 27th and SE 28th Street.

December 12, 2024- Progress continued this week, with crews installing more Silva Cells along the east side of 80th Avenue north of SE 28th Street. These new cells will provide room for the roots of the new street trees to develop under the new sidewalk. Crews also poured more areas of new concrete curb, gutter, and sidewalk. Next week should see additional grading work for sidewalks in the SE 28th Street intersection area and hopefully additional curb, gutter, sidewalk and ADA ramp pours, however the concrete work is weather dependent.

October 17, 2024- This week, City contractors poured sections of new sidewalk along the east side of 80th Avenue SE at SE 32nd Street. City contractors also patched back asphalt sections that had been removed to install the new curb and gutter. Next week, crews plan to continue pouring new sidewalk between SE 30th and SE 32nd Streets; however, this work is weather dependent.

80th Ave patching along new curbs80th Ave patching along new curbs


80th Ave sidewalk pour80th Ave sidewalk pour


80th Ave sidewalk80th Ave sidewalk


October 10, 2024- This week, City contractors poured sections of new sidewalk along the east side of 80th Avenue SE at SE 32nd Street. Next week, crews plan to continue pouring new sidewalks between SE 30th and SE 32nd Streets; however, this work is weather dependent. Also next week, crews will be removing two street trees on the east side of 80th Avenue SE just south of SE 28th Street.

October 4, 2024- This week, City contractors poured additional new curb and gutter along the east side of 80th Avenue SE at SE 32nd Street. They also continued with installing electrical conduit for the new illumination system and also started grading for new sidewalks. Later next week, crews hope to begin pouring new sidewalk between SE 30th and SE 32nd Streets.

80th Curb and Gutter80th Curb and Gutter


80th Curb and Gutter80th Curb and Gutter


80th Curb and Gutter80th Curb and Gutter


September 26, 2024- This week, the City’s contractor, Always Active Services, placed crushed rock and graded for curb, gutter and sidewalk along the east side of 80th Avenue SE at SE 32nd Street. They also continued excavation and installation of new electrical conduit for the new illumination system and their subcontractor, Custom Concrete, began pouring new curb and gutter. Next week, crews will continue with grading, conduit installation and curb and gutter between SE 30th and SE 32nd Streets.

Pouring Curb & Gutter on 80th AvePouring Curb & Gutter on 80th Ave


Pouring Curb & Gutter on SE 32ndPouring Curb & Gutter on SE 32nd



September 19, 2024- This week, the City’s contractor, Always Active Services, removed asphalt along the east side of 80th Avenue SE at SE 32nd Street. They also started excavation and installation of new electrical conduit for the new illumination system. Next week, crews will continue removals and conduit installation between SE 30th and SE 32nd Streets. They will also begin placing crushed rock and grading for new curb, gutter and sidewalk.

80th Asphalt Removal80th Asphalt Removal


Trenching for Conduit Trenching for Conduit


Conduit TrenchConduit Trench


September 12, 2024 - This week, the City’s contractor, Always Active Services, started removing the old concrete curb, gutter, and sidewalk along the east side of 80th Avenue SE, between SE 30th and SE 32nd Streets. Next week, crews will continue removals and start underground utility work for the new street lighting between SE 30th and SE 32nd Streets. Following the utility work new concrete curb, gutter, and sidewalk will be poured.

80th Curb & Gutter Removal80th Curb & Gutter Removal
80th Curb & Gutter Removal80th Curb & Gutter Removal
80th Sidewalk Removal80th Sidewalk Removal
80th Vegetation Removal80th Vegetation Removal

September 6, 2024 - This week, the City’s contractor, Always Active Services, removed trees along the east side of 80th Avenue SE, between SE 30th and SE 32nd Streets due to large root masses that are heaving the existing sidewalk. The trees being removed will be replaced with new trees this fall/winter after the construction of the new sidewalk is completed. Next week, crews will begin sidewalk removals and underground utility work for the new street lighting between SE 30th and SE 32nd Streets.

80th Tree Removal




Removed Tree on 80thRemoved Tree on 80th




Subcontractor in Tree Removing LimbsSubcontractor in Tree Removing Limbs