Construction Updates

Week of 10.14.24
The contractor continued its pause in construction. Next week, the landscaping subcontractor is scheduled to begin work on irrigation and plantings and that work should be completed in mid-November.

Week of 9.9.24

This week, pavement markings were installed, new fencing was completed, and the path was reopened to normal pedestrian and bicycle use. Landscape, lighting, signage, and other minor work will be addressed in the next several weeks.

Pavement MarkingsPavement Markings



Week of 9.2.24

This week, contractor crews installed asphalt pavement and wood post and rail fencing. Pavement markings will be installed starting next Monday. Temporary construction fencing around the ballfield area should be removed next week. Lighting, landscaping, signage, and irrigation are planned for installation in the next three to four weeks.

finishing asphaltfinishing asphalt
grading asphaltgrading asphalt


New fencingNew fencing


Week of 8.26.24

This week, contractor crews installed the new concrete pathway through the ballfield area. The path consists of two different colors of concrete, poured over a two-day period. Next week the contractor will focus on placing topsoil and installing post-and-rail fencing. Landscaping, traffic signs, and pavement markings will follow in mid-September.

Brooming
dark panels completeddark panels completed
finishing infill panelfinishing infill panel
pumping concrete viewpumping concrete view
pumping concretepumping concrete




Week of 8.19.24

The contractor excavated for the new concrete pathway and conduit for new trail lighting. The concrete subcontractor installed forms for concrete and the general contractor continued trail shoulder restoration from previous weeks. Next week will be focused on concrete and electrical installation. Following that, soil amendments will be added in preparation for landscaping.

Ballfield connection
Forming for concrete pathForming for concrete path
Grading baseGrading base

Surveying for pathSurveying for path









Week of 8.12.24

The contractor fenced off the work area at Feroglia Fields and began demolition for the trail and landscape improvements there. Asphalt and sod were excavated and hauled off. Next week, the concrete subcontractor will start installing concrete forms and the electrical subcontractor will start laying out their conduit for the light pole. Meanwhile the general contractor will finish up the trail shoulder restoration from last week.

Demolished MaterialDemolished Material
loading materialloading material


Week of 8.5.24

The contractor began shoulder restoration on portions of the trail by cutting back heavy vegetation and placing a gravel-soil mix that will allow grass to grow along the trail edge, providing pedestrians extra room to step off the trail. Next week, the contractor will close the trail in the ballfield area and reroute trail traffic through the south and east sides of the fields. This closure will be in place for several weeks while the new concrete trail is installed.

grubbing + clearing trail edgegrubbing + clearing trail edge


placing shoulder materialplacing shoulder material



shoulder rough gradedshoulder rough graded




Week of 7.29.24

The Contractor mobilized to the site and began grubbing planting areas this week. They have discontinued work for August 1 – 5 to avoid conflicts with Seafair activity. Next week they will begin shoulder restoration on portions of the trail. A gravel-soil mix will be placed that will allow grass to grow along the trail edge, providing pedestrians extra room to step off the trail. Neighbors abutting this work have been notified.


Week of 7.22.24

The City conducted the pre-construction meeting and completed the WSDOT construction permit this week. Staff placed project advisory signs at strategic locations along the trail to notify users of the construction. The contractor is scheduled to start work Monday, July 29th, but no work will occur from August 1st to 5th due to Seafair. Project completion is estimated at the end of September.

Week of 7.15.24

A preconstruction meeting with the contractor and City staff is scheduled for next week. Trail work is expected to start the week of July 29.

Share Construction Updates on Facebook Share Construction Updates on Twitter Share Construction Updates on Linkedin Email Construction Updates link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>