Work continues to prepare for construction of the new Bike Skills Area at Deane’s Children’s Park. Here are a few highlights from progress over the last several weeks.
Site Preparation
The site for the BSA is looking great thanks to work by volunteers and Parks Maintenance staff, who have been cleaning up the area throughout the summer! You may have also noticed construction fencing around the project site; this was installed in July and will remain up through construction. Project awareness signs will also be posted soon. Volunteers are still needed to assist with mulching around trees before construction begins. Reach out to Jordan Fischer, jordan.fischer@mercerisland.gov, to volunteer!
Permitting
The comment period for the Critical Area Review 2 and SEPA Review closed on July 20, and the project team is awaiting a determination from the Community Planning and Development department. Details about the determination will be shared on Let’s Talk once issued.
BSA Signage
Staff reviewed BSA rules and other signage copy with WCIA, the City’s insurance provider, this month. The City is also creating new signage to post at trail entrances and other key locations in the Island Crest Park system. Those signs will be installed before the BSA opens.
ICP Trail Counts
Trail counts to better understand usage in Island Crest Park resume this month. If you see a volunteer or staff member in the park conducting counts, please say hello!
This project is complete. Please visit the Bike Skills Area page on the city website for maintenance, closure, and other information.