It's coming!

Mercerdale play equipment is coming. Another supply chain shortage in the color powder coating has caused further delay, so the opening of the playground will likely be in early 2022. Here is an updated timeline:

  • Site work is currently underway and expected to continue thru Thanksgiving.
  • The new Mercerdale Train sculpture is scheduled to arrive early December.
  • Mid-December the rest of the playground equipment is scheduled to arrive. Our team is actively working to push this to arrive earlier. With the foundation work currently happening, this should go together in about a week.
  • Once the equipment is installed, the poured-in-place rubber surfacing will be applied. This is installation requires decent weather…not the storms we’ve been experiencing this fall. Let’s hope the Pineapple Express is done moving thru our area for the installation!
  • Playground grass (synthetic grass) is scheduled to be installed near the end of December.


Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>