Key Dates
July 01 2025
City Council conducts first reading of bond ordinance and revises project budget to $103,160,000.
June 17 2025
City Council approves the PSM Schematic Design and sets the project budget at $103,900,000.
September 2024 → June 2025
The PSM Design team conducts the Schematic Design phase of the PSM Facility.
March → September 2024
The City conducts the “pre-design” phase for the PSM Facility with the architect team from Northwest Studio.
March 2024
City Council directed the City Manager at the March 1, 2024 Planning Session to commence planning and design for a new Public Safety and Maintenance Facility (PSM) on the current City Hall Campus.
February 2024
City Manager recommends City Council prioritize the Public Works Building for replacement in response to facilities condition assessment.
October → December 2023
City staff and consultants continue working on temporary and long-term solutions.
July 18 2023