Spring 2025 Construction Update

The Xing Hua project has progressed from shoring, foundation, and subgrade construction to placement of the post-tensioned concrete decks. Through February and early March, the concrete pedestal construction of the ground level was placed. This concrete deck will be re-shored following the removal of formwork, while tendons placed in the concrete are tensioned. Following completion of the concrete pedestal, wood-framed construction of the upper levels will follow.

Share Spring 2025 Construction Update on Facebook Share Spring 2025 Construction Update on Twitter Share Spring 2025 Construction Update on Linkedin Email Spring 2025 Construction Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>