Long-Range Facility Planning/City Hall Closure

Share Long-Range Facility Planning/City Hall Closure on Facebook Share Long-Range Facility Planning/City Hall Closure on Twitter Share Long-Range Facility Planning/City Hall Closure on Linkedin Email Long-Range Facility Planning/City Hall Closure link
Mercer Island City Hall

Project Overview

In early 2023, the City of Mercer Island began working on Facilities Conditions Assessments to guide future investment decisions for City facilities and the development of a Long-Range Facilities Plan. These assessments include Mercer Island City Hall, the Public Works Building, the Mercer Island Community and Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop building, and the former Tully’s Building. A second phase will include Facility Conditions Assessments for Fire Station 91, Fire Station 92, and the Mercer Island Community and Event Center.

The assessments will be used to prioritize a comprehensive plan to maintain, repair or replace these buildings to ensure City facilities can deliver municipal programs and services for the next 50 years.

City Hall Closure – April 2023

In April 2023, and in the midst of beginning the Facilities Conditions Assessments, staff visually identified broken floor tiles and flooring adhesive in the basement mechanical room at City Hall. Immediate testing of the materials confirmed that both the tiles and the adhesive were asbestos containing materials. This mechanical room houses one of the building's two primary air handling units, a key component of the heating, ventilation, and air conditioning (HVAC) system. To ensure the safety of City staff and visitors, City Hall was immediately closed while further testing was conducted to determine if asbestos fibers were present in other areas of the facility.

The City hired PBS Engineering and Environmental (PBS) to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing. Testing has resulted in asbestos detection in several locations in the building, including in the HVAC system. No airborne asbestos was detected during air quality tests.

City staff and outside experts worked extensively to identify solutions to address the asbestos contamination and evaluate the best path forward for City Hall. Two scenarios for re-occupying the City Hall building, either fully or partially, were evaluated for timeline, preliminary costs, and impact to City operations. Unfortunately, the cost of both scenarios to re-occupy City Hall exceeded the benefits due to the age and condition of the building.

Islanders are encouraged to stay informed and engaged with the facilities planning process here on Let’s Talk. You can review the Frequently Asked Questions, which includes more information about this project and the closure of City Hall, and submit questions for a response using the Ask a Question feature.

Project Overview

In early 2023, the City of Mercer Island began working on Facilities Conditions Assessments to guide future investment decisions for City facilities and the development of a Long-Range Facilities Plan. These assessments include Mercer Island City Hall, the Public Works Building, the Mercer Island Community and Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop building, and the former Tully’s Building. A second phase will include Facility Conditions Assessments for Fire Station 91, Fire Station 92, and the Mercer Island Community and Event Center.

The assessments will be used to prioritize a comprehensive plan to maintain, repair or replace these buildings to ensure City facilities can deliver municipal programs and services for the next 50 years.

City Hall Closure – April 2023

In April 2023, and in the midst of beginning the Facilities Conditions Assessments, staff visually identified broken floor tiles and flooring adhesive in the basement mechanical room at City Hall. Immediate testing of the materials confirmed that both the tiles and the adhesive were asbestos containing materials. This mechanical room houses one of the building's two primary air handling units, a key component of the heating, ventilation, and air conditioning (HVAC) system. To ensure the safety of City staff and visitors, City Hall was immediately closed while further testing was conducted to determine if asbestos fibers were present in other areas of the facility.

The City hired PBS Engineering and Environmental (PBS) to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing. Testing has resulted in asbestos detection in several locations in the building, including in the HVAC system. No airborne asbestos was detected during air quality tests.

City staff and outside experts worked extensively to identify solutions to address the asbestos contamination and evaluate the best path forward for City Hall. Two scenarios for re-occupying the City Hall building, either fully or partially, were evaluated for timeline, preliminary costs, and impact to City operations. Unfortunately, the cost of both scenarios to re-occupy City Hall exceeded the benefits due to the age and condition of the building.

Islanders are encouraged to stay informed and engaged with the facilities planning process here on Let’s Talk. You can review the Frequently Asked Questions, which includes more information about this project and the closure of City Hall, and submit questions for a response using the Ask a Question feature.

  • A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building

    Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Facebook Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Twitter Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Linkedin Email A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building link

    Last week, your City Council took a pivotal step in the future of City operations by unanimously approving the costing and design for a new Public Safety and Maintenance Building on the current City Hall campus. This facility would house the City’s Police Department and public works crews, providing a safe and functional facility that meets the urgent needs of our City today.

    The motion, put forward by Deputy Mayor Rosenbaum during the Council's annual planning session, demonstrates a collective commitment to enhancing the safety and well-being of our employees and community. The existing Public Works Building is well beyond its useful life and hasn’t met our needs for some time. The closure of City Hall only exacerbated this challenge, displacing staff across all teams and the specialized functions of our Police Department.

    Careful evaluation and planning brought us to this path forward. Building a new facility serving both our police and public works teams meets the unique needs of both departments in a much more efficient manner. The City Manager will now commence planning for this new facility, with a preliminary scope and cost estimate due in Q2 2024.

    What does this mean for a future City Hall and the rest of the City’s teams? We continue to discuss opportunities for a home in Town Center – a shift that represents a generational investment in a more accessible, efficient, and community-focused downtown City Hall. These decisions are not just about buildings and staffing but about laying the groundwork for a more connected, safe, and vibrant Mercer Island. We’ll continue to keep you updated on Let’s Talk, the City’s public engagement platform.

    The success of last week’s Council Planning Session reflects extensive preparation by City staff and the Council's supportive and collaborative spirit aimed at recognizing the valuable contributions of all City employees. Together, we are able to navigate the complexities of our current challenges and make informed decisions that reflect the priorities and needs of you, our residents.

    A great deal of dedication, insightful discussions, and strategic decisions have set in motion what we believe will be a very positive trajectory for the City of Mercer Island. These initiatives will bring about meaningful and positive changes in our community – we look forward to working across the Island to articulate this vision and we’re excited to see the impact our collective efforts will have for the Island’s future.

    Mercer Island City Council

    Mayor Salim Nice
    Deputy Mayor Dave Rosenbaum
    Councilmember Lisa Anderl
    Councilmember Jake Jacobson
    Councilmember Craig Reynolds
    Councilmember Wendy Weiker
    Councilmember Ted Weinberg

  • Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building

    Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Facebook Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Twitter Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Linkedin Email Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building link

    At the City Council Planning Session on March 1, 2024, the Council unanimously approved AB 6420 directing the City Manager to commence planning for a new Public Safety and Maintenance Building on the current City Hall campus. This new facility will replace the existing Public Works Building and provide a new combined home for the City’s Public Works teams and Police Department.

    A preliminary scope and cost estimate will be presented to the Council in Q2 2024.

    In early 2023, the City began a process to complete Facility Conditions Assessments (FCAs) for various municipal buildings, including City Hall, the Public Works Building, the Annex Building at the Mercer Island Community & Event Center, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop, and the former Tully’s Building. Due to the emergency closure of City Hall in April 2023, this work was reprioritized to meet the most pressing needs.

    Given the age and condition of the Public Works Building, the City Manager directed staff and consultants to complete a FCA for this building, while pausing assessment work on the other buildings.

    The assessment identified multiple systems that are failing or in need of significant repair or investment. This information was presented to the City Council on February 6, 2024 (AB 6402).

    Combined with the City’s urgent space needs for teams displaced by the City Hall closure, the City Manager recommended that the Council prioritize the Public Works Building for replacement. Council’s direction allows the City Manager to proceed with building this new facility on the existing campus.

    More information about this project will be shared soon. You can review the full Let’s Talk page to learn more about the City’s Long Range Facility Planning work.

  • Council to Review Town Center Commuter Parking Site Concept

    Share Council to Review Town Center Commuter Parking Site Concept on Facebook Share Council to Review Town Center Commuter Parking Site Concept on Twitter Share Council to Review Town Center Commuter Parking Site Concept on Linkedin Email Council to Review Town Center Commuter Parking Site Concept link

    In 2017, the City entered into a settlement agreement with Sound Transit to offset local impacts of the East Link light rail project. As part of this agreement, $4.41 million was dedicated for long term regional transit commuter parking projects near the new Light Rail Station in Town Center.

    At the February 20 regular meeting, the City Council will review a recommendation and preferred site concept for a commuter parking project in the Town Center, presented by City Manager Jessi Bon. The Commuter Parking Project site consists of three different parcels, including the former Tully’s Property, acquired and assembled over multiple years for the purpose of providing long-term regional transit commuter parking.

    You can attend the February 20 council meeting in-person or virtually to watch the discussion.

  • Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment

    Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Facebook Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Twitter Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Linkedin Email Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment link

    As part of the process to evaluate the condition of municipal buildings and develop a plan for their future, the City Council will review preliminary findings from the Public Works Building Facility Conditions Assessment at the February 6, 2024 regular meeting. Staff and consultants will present the preliminary findings from the assessment and answer councilmember questions.

    The Public Works building, located behind City Hall, was constructed primarily as a workshop and mechanic facility in 1981. Since then, it's been repurposed several times to meet the changing needs of City operations. The building is 15,350 square feet and currently houses the following operational and administrative teams made up of Full Time Equivalent Employees (FTEs) and Limited Term Employees (LTEs):

    • Right-of-Way and Stormwater Team (10 FTEs)
    • Water Utility (8.5 FTEs, 3 LTEs)
    • Sewer Utility (6.5 FTEs)
    • Parks Maintenance (10 FTEs)
    • Support Services Team (3 FTEs, 1 LTE)
    • Public Works Engineering and Administration Teams (19 FTEs)

    Following the closure of City Hall in April 2023, the City’s Utility Billing Team was also re-located at the Public Works Building (3 FTEs). In total, there are 64 employees (FTE and LTE equivalents) and 15 to 20 seasonal employees who currently operate out of this facility.

    The Facility Conditions Assessment process identified the following preliminary findings about the building's condition:

    • Roofing is at the end of its projected useful life and leaks are prevalent throughout the building.
    • The current 150kVA electrical service is insufficient to support the current needs of the facility.
    • The electrical distribution system is aged, with some critical components at the end-of-life.
    • The original HVAC system is mostly obsolete throughout the building, delivering poor performance, high energy consumption, and marginal air quality.
    • Plumbing is inadequate to meet the staffing levels for the building, requiring the use of portable toilets to meet sanitation requirements.

    Based on the findings from the FCA and known operational deficiencies, the City Manager is recommending the Public Works Building be prioritized for replacement. Staff and consultants are currently working on preliminary replacement strategies for the City Hall Building and the recommendation is to combine the planning process to address replacement of both buildings.

    While the initial assessment is preliminary, staff and consultants are finalizing the assessment and cost estimates - they expect to have this work complete by June 2024. Staff will identify critical system repairs needed to extend the life of the building temporarily (for five to ten years) while replacement strategies are developed. Staff will present those strategies to the City Council as part of the upcoming 2025-2026 Biennial Budget Development process.

    A follow-up discussion on City facilities is planned for the March 1, 2024, City Council Planning Session. This presentation and discussion will primarily focus on the replacement strategies for City Hall and the Public Works Building.

    You can review the City Council Agenda Bill 6402 for additional details on this presentation. The preliminary report is also available online.

  • An Update on City Operations, Planning Continues for City Hall

    Share An Update on City Operations, Planning Continues for City Hall on Facebook Share An Update on City Operations, Planning Continues for City Hall on Twitter Share An Update on City Operations, Planning Continues for City Hall on Linkedin Email An Update on City Operations, Planning Continues for City Hall link

    Earlier this year, the City Council voted to permanently close City Hall. City staff, the City Council, and outside experts have since been hard at work planning for a solution to the City Hall closure, as part of the City’s existing Long Range Facility Planning process.

    While City Hall may be closed, most City operations continue as normal. Approximately 80% of City employees continue to work in-person on Mercer Island, whether from shared workspaces in administrative areas of the Community Center, the Maintenance Building, the Luther Burbank Administrative Building, or out in the field. Remaining staff are working from a combination of home offices and in shared/rotating office spaces on-Island, often holding meetings at the Community Center or at other locations.

    The City is standing up temporary facility solutions for specialized operations that were displaced by the closure of City Hall, including City Court and Police Department facilities:

    Municipal Court: At the November 7 City Council meeting, the Council approved a lease agreement with the City of Newcastle allowing Mercer Island Municipal Court to temporarily operate out of Newcastle City Hall. Court staff are currently arranging operating details, with information on accessing court services in Newcastle coming soon.

    Police Department: While our Police Department staff have worked hard to continue normal levels of service without access to the Police wing of City Hall, day-to-day operations have been challenging for our officers. At the November 21 City Council meeting, the Council reviewed a budget allocation for Police Department portable facility solutions. These temporary facilities will provide dedicated spaces for the many specialized needs of a police department and greatly ease day-to-day challenges for our officers and staff.

    Work on a long-term replacement strategy for City Hall continues. The City will consider a wide range of options that will result in a responsible, efficient, and sustainable future for City Hall operations. While much of the planning related to real estate transactions must be conducted confidentially through the City’s broker, community engagement on the long-term options to replace City Hall is anticipated in 2024. Islanders are encouraged to stay updated and engaged with this project here on Let’s Talk.

    As always, City staff remain available and ready to assist you. For the quickest and fastest service, community members should contact the City of Mercer Island Customer Service Team at 206-275-7600 or at customerservice@mercerisland.gov.

  • A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall

    Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Facebook Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Twitter Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Linkedin Email A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall link

    October 4, 2023

    For the past six months, my office – alongside a team of staff and outside experts – have been working to address the unexpected closure of City Hall due to the discovery of asbestos in the building’s HVAC system. At last night’s City Council meeting, the Council unanimously supported my recommendation to permanently close City Hall. I want to provide an update on why that decision was made and what’s ahead.

    In April of this year, maintenance staff identified broken floor tiles in the City Hall basement mechanical room and these tiles were confirmed to contain asbestos. Because this mechanical room houses key components of the building’s HVAC system, including an air handling unit, City Hall was immediately closed while further testing was conducted.

    From April through July, the City worked with PBS Engineering and Environmental to conduct comprehensive asbestos testing of the City Hall building, which included air sample, settled dust, and bulk material testing, with a focus on the HVAC system. Fortunately, no asbestos fibers were identified in any air samples, but settled dust tests did confirm asbestos is present above background levels (which requires abatement) in several segments of the HVAC system. Based on these findings, the HVAC system was turned off and has been inoperable since mid-May.

    The location of both confirmed and likely asbestos in the City Hall HVAC system makes abatement extremely difficult, costly, and time-consuming. There is limited accessibility to some areas of the HVAC system, as many of the oldest ducts are encapsulated behind heavy plastic sheeting, fiberglass batt insulation, and/or multiple layers of ceiling material. The testing inside the HVAC system was taken as far as it could but was halted in early summer due to limited access to the remaining areas of the system. The presence of fiberglass batt insulation throughout the system also means it is not possible to clean and return the existing system to operation. The only option to address the HVAC asbestos contamination is a full replacement of the system, and subsequently, the associated infrastructure (ceiling, lighting, cabling, etc.).

    City staff and consultants provided a comprehensive report to the City Council on these findings at the July 18, 2023, City Council meeting and that information is available here on Let’s Talk.

    With that information in hand, we evaluated different scenarios for re-occupying City Hall, either fully or partially. The preliminary cost estimate to re-occupy City Hall is in excess of $10 million, with an estimated timeline of nearly two years to complete the work. We also considered a more modest approach and evaluated re-occupancy of the police portion of the building only, and those cost estimates are in excess of $4 million. While these costs alone likely exceed the anticipated return on investment, there are other factors that were considered in the decision to permanently close City Hall.

    City Hall was built in 1957 and has been repaired and renovated over the years, with the last major renovation occurring in the late 1980s. Prior to the asbestos situation, the City Council recognized the need for a replacement strategy for this building, and in early 2023, the City began working on a Facilities Conditions Assessment to guide long-term decisions. The initial assessment work highlighted the many other matters of concern related to the long-term use of City Hall. The building suffers from structural and seismic deficiencies. Almost all the interior walls have been identified as lacking lateral bracing and, unless reinforced, are at risk of failure in the event of seismic activity, potentially rendering the building inoperable. Additionally, the building does not conform with current energy or building code requirements, and multiple building systems are failing or need to be substantially replaced.

    Given this additional information and the anticipated investment needed to re-occupy City Hall and bring it up to current standards, the decision was made to permanently close the building and turn our attention to identifying a replacement strategy.

    What does this mean for City services in the short-term? While we’re still working through our day-to-day operations, I can tell you that City staff remain hard at work and almost all public services continue to be available as normal. I’m incredibly grateful to our staff teams for their flexibility and creativity as we’ve figured out how to double up in offices, move equipment to other buildings, and sort through this challenge. Approximately 80% of our team continues to work in-person on Mercer Island, whether from shared workspaces in administrative areas of the Community Center, the Maintenance Building, the Luther Burbank Administrative Building, or out in the field. The remaining staff are working from a combination of home offices and in shared/rotating office spaces on-Island, often holding meetings at the Community Center or at other locations.

    We encourage all Islanders to review our Let’s Talk Page – you can learn more about the many details involved in the decision to close City Hall and ask a question that hasn’t yet been answered. As always, our Customer Service Team stands ready to assist you in answering questions or accessing City services.

    While having to suddenly close City Hall was unexpected and unfortunate, we are turning our attention to the critical work involved in identifying a long-term replacement strategy and discussions with the community and the City Council are anticipated to begin in 2024.

    Thank you,

    Jessi Bon
    Mercer Island City Manager


  • October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall

    Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Facebook Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Twitter Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Linkedin Email October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall link

    At the October 3, 2023, City Council meeting, City Manager Jessi Bon will recommend that the City cease operations at Mercer Island City Hall and permanently close the building (see Resolution No. 1650). This recommendation is due to the discovery of asbestos containing materials, primarily in the City Hall HVAC system, that cannot be easily remediated.

    The City Manager has organized specific staff teams to address the many issues and work items related to the closure of City Hall. This includes moving personal items out of City Hall, technology transitions, support for work groups that are the most impacted by the closure including Police and Municipal Court, and other matters.

    • At the October 17, 2023 City Council meeting, the Council will review and consider an agenda bill approving an Interlocal Agreement and lease with the City of Newcastle to house Municipal Court operations. After an exhaustive search for temporary leased space, the City Manager is recommending leasing Newcastle Council Chambers for court proceedings and available office space in the Newcastle City Hall building for court staff offices.
    • Staff are also working to address the impacts to the Police Department and are in the process of implementing a plan to place temporary modular facilities in the City Hall parking lot for short-term support of police operations. Staff will brief City Council on the work to re-house the Police Department at a future City Council meeting.
    • Long-term planning work related to the replacement of City Hall is underway. Discussions with the City Council and the community are planned for 2024.

    Staff and consulting teams also continue to work on the logistics of preparing City Hall for permanent closure, including planning for the storage of furniture, equipment, and supplies, managing paper records, discarding unneeded items, and the retrieval of personal items. The HVAC system at City Hall, for example, has been inactive since mid-May and cannot be operated safely. Since the building doesn’t have a functional heating system, water service at City Hall has been shut off and the plumbing system drained to help avoid potential frozen pipes should the region experience an early-fall cold snap.

    Stay updated on both current City operations and the planning for a permanent City Hall solution here on Let’s Talk. Islanders are encouraged to review the Frequently Asked Questions below, which includes information on what ideas have been considered and additional details. You can also submit questions for a response using the Ask a Question feature.

  • July 18, 2023 – Update to City Council on City Hall Closure and Next Steps

    Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Facebook Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Twitter Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Linkedin Email July 18, 2023 – Update to City Council on City Hall Closure and Next Steps link

    At the July 18, 2023 City Council meeting, representatives from PBS Engineering and Environmental (PBS) provided an overview of the environmental assessment work performed at City Hall and reviewed the findings. Here’s what was presented:

    Testing Methods and Results

    Following the initial asbestos testing, the City hired PBS to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing, with hundreds of samples collected across all test types.

    Air Sampling

    The intent of air sampling is to screen interior air for potential asbestos fibers. Air samples were collected from locations throughout the building, using high-volume air sampling pumps and analyzed using the NIOSH 7402 method, which uses Transmission Electron Microscopy (TEM) and reports findings in concentrations of fibers per cm3. No asbestos fibers were identified in the collected air samples.

    Settled Dust Sampling

    The intent of this sampling is to evaluate surface dust in the building and mechanical system for potential asbestos content. PBS collected settled dust samples at representative locations throughout the interior of City Hall and inside the HVAC system. Each sample was collected using an air sampling pump to draw dust from a 100 cm2 area.

    Samples were analyzed using the ASTM D 5575-09 method, which uses Transmission Electron Microscopy (TEM) and reports findings in concentrations of structures per square centimeter (s/cm2). Findings are reported based on the size of any asbestos identified, grouped by between 0.5 and 5 microns, and those larger than 5 microns.

    ‘Background levels’ of asbestos structures in accumulated dust range from an average of 1,000 s/cm2 in non-industrial areas to 10,000 s/cm2 in cities and industrial areas where asbestos materials are common. Levels above 10,000 s/cm2 are generally considered to be “above background” in any geographical location. There are no regulatory thresholds for the amount of asbestos in surface dust.

    Asbestos concentrations in excess of 10,000 s/cm2 were identified in six of the samples, all of which were associated with the HVAC system.

    Bulk Asbestos Sampling

    PBS took 84 samples from various materials for the presence of asbestos. This has been conducted to confirm asbestos content in select building materials.

    Samples were analyzed according to either EPA Method 600R-93/116 using Polarized Light Microscopy (PLM) or EPA Method 600R-93/116 TEM Bulk Semi-Quantitative.

    In addition to the various flooring and adhesive materials that tested positive for the presence of asbestos, three bulk samples taken from HVAC filters contained trace amounts of asbestos, and two window-glazing putty samples tested positive.

    Limitations on Testing and Inspection

    One goal of this wide-ranging testing was to create a comprehensive survey of conditions inside the HVAC system. However, field analysis found that many of the oldest ducts are encapsulated behind heavy plastic sheeting and fiberglass batt insulation and/or multiple layers of ceiling material. Accessing these areas for testing will require coordinated and costly deconstruction of multiple building systems including but not limited to electrical, data and low-voltage cabling, plumbing, ceiling grid, and insulation. The testing inside the HVAC system was taken as far as it could but was halted due to limited access to the remaining areas.

    In conjunction with the targeted HVAC testing, a building-wide “Good Faith Inspection” was conducted on June 27, 2023 to detect, identify, and catalog any unknown asbestos-containing materials. The goal of the inspection was a full-building analysis, but the scope of the investigation was also limited due to the inaccessibility of much of the attic and roof structure of the building. No previously unknown asbestos-containing materials were found in the areas that were accessible for surveying.

    While the floor tiles and adhesive found in the basement mechanical room alerted staff to the asbestos issue and prompted extensive testing in the building, these items are not likely to be the sole source of asbestos detected in portions of the HVAC system. Additional sources of asbestos contamination have not been definitively identified, and likely will not be uncovered by further testing. Based on the varying levels and locations of asbestos identified through the testing completed to date, PBS consultants believe there is a high probability that one or more sources of contamination contributed to the issue over the life of the building. Further, there is a high likelihood that the original asbestos-containing materials were removed during a previous renovation in the late 1980s.

    Abatement

    Abatement, which is the removal of contaminated materials and equipment by a specialized contractor, has only been completed in a limited area of the basement of City Hall. Specifically, the basement mechanical room floor with asbestos containing broken tiles and adhesive was abated by a licensed contractor in mid-May, with post-abatement sampling of the floor confirming that there are no longer detectable traces of asbestos present. The HVAC system at City Hall remains unabated and turned off. Unless it is abated, it must remain off.

    Potential Solutions to Re-Occupy City Hall

    Northwest Studio, the City’s architect team, presented two preliminary scenarios to the City Council to re-occupy City Hall:

    The first scenario was a full re-occupancy of City Hall. This work would require abatement of the floor tiles in the basement mechanical room, replacement of the HVAC hydronic and ventilation system, and the replacement of various building infrastructure required by replacement of the HVAC system (ceilings, light fixtures, cabling, etc.). The preliminary cost estimate to re-occupy City Hall under this scenario is $10 million with an estimated timeline of nearly two years to complete the work. This cost estimate does not include full abatement costs or softs costs such as design, engineering, and project management costs.

    The second scenario was to investigate the possibility of re-occupying only the Police Department areas of City Hall for seven years while longer-term options were investigated. The team looked at partitioning the existing Police Department spaces from the remainder of the City Hall building, abating those spaces, removing the existing HVAC system, and installing a contemporary system to serve this occupancy. The preliminary cost estimate to abate and re-occupy the Police Department portion of City Hall is over $4 million with an estimated timeline of 12 to 18 months to complete the work. This cost estimate does not include full abatement costs or softs costs such as design, engineering, and project management costs.

    Upon learning of the initial cost estimates to abate and re-occupy the City Hall building, and in consideration of the age and condition of the building, Councilmembers indicated during discussions at the July 18, 2023 City Council meeting that the costs to re-occupy City Hall outweighed the benefits of re-opening the building.

  • City Conducts Request for Proposals Process for Long-Range Facilities Planning

    Share City Conducts Request for Proposals Process for Long-Range Facilities Planning on Facebook Share City Conducts Request for Proposals Process for Long-Range Facilities Planning on Twitter Share City Conducts Request for Proposals Process for Long-Range Facilities Planning on Linkedin Email City Conducts Request for Proposals Process for Long-Range Facilities Planning link

    In December of 2022, the City launched a Request for Proposals (RFP) process to complete a Facilities Conditions Assessment for various municipal buildings and to lead the development of a Long-Range Facilities Plan for select City facilities. The scope of work includes Mercer Island City Hall, the Public Works Building, the Mercer Island Community & Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop, and the former Tully’s Building.

    The project is structured in two phases, the first being the Facilities Conditions Assessment performed in 2023. The assessment and accompanying data and analysis will be used to prioritize a comprehensive repair, alteration, and improvement budget for extending building life for 50 years. The outcomes from the Facilities Conditions Assessment will help shape and guide the second phase of work, anticipated in 2024, which will include development of a Long-Range Facilities Plan for select facilities.

    The City sent the Request for Proposals to 29 firms known to have experience or expertise in building condition analysis and future facilities planning. Eight firms responded and the City selected four of these to interview. Based on these interviews by a panel of City staff, Northwest Studio was selected for the Facilities Conditions Assessment and Long-Range Facilities Planning project in March 2023.

    The scope of work and phasing has changed slightly due to evolving needs related to the emergency closure of City Hall. The long-term planning portion of the project will include scenarios for replacement of City Hall, as well as meeting the original intent of guiding City Council decisions on other City buildings.

  • Frequently Asked Questions

    Share Frequently Asked Questions on Facebook Share Frequently Asked Questions on Twitter Share Frequently Asked Questions on Linkedin Email Frequently Asked Questions link

    These frequently asked questions (FAQ) can also be found in the FAQ section.

    City Hall Facility Asbestos Discovery and Abatement

    Q: How was the asbestos discovered?
    A: Staff visually identified broken floor tiles and flooring adhesive in the basement mechanical room, which had a similar appearance to other asbestos-containing materials previously abated in City Hall. Professional testing was then conducted which confirmed the materials were asbestos-containing on April 17, 2023.

    The mechanical room houses one of the building’s two primary air handling units (AHU), a key component of the HVAC system. To ensure the safety of City staff and visitors, City Hall was closed immediately while further testing was conducted to determine if asbestos fibers were present in other areas of the facility.

    Q: Has any asbestos remediation been carried out yet?
    A: Abatement, which is the removal of contaminated materials and equipment by a specialized contractor, has only been completed in a limited area of the basement of City Hall. Specifically, the basement mechanical room floor with asbestos-containing broken tiles and adhesive was abated by a licensed contractor in mid-May, however the HVAC system at City Hall remains unabated and inactive due to the subsequent expense and complexity of abating that system.

    Q: What would it cost to conduct asbestos abatement so City Hall could reopen?

    A: The preliminary cost estimate to re-occupy City Hall is $10 million with an estimated timeline of nearly two years to complete the work. This cost estimate does not include full abatement costs or soft costs such as design, engineering, and project management costs.

    Q: Why is the cost of abatement and re-occupancy so high?

    A: The work to re-occupy City Hall would include the required abatement of asbestos-containing floor tiles throughout the building, replacement of the HVAC hydronic and ventilation system, and the replacement of various building infrastructure required by replacement of the HVAC system (ceilings, light fixtures, cabling, etc.).

    Q: Why can’t the HVAC system be abated (cleaned) instead of being fully replaced? What about portable or temporary systems?
    A: Commercial HVAC systems are complex and must meet a variety of health and safety standards. Due to the intricate nature of the internal components of the HVAC air handling units, the presence of fiberglass batt insulation inside many of the system’s ducts, and the age and volume of dust build-up present throughout the system, it is not possible to clean and return the existing system to operation. The only option is a full retrofit replacement.

    Portable systems are not a viable option as they do not meet current energy code requirements and would require extensive modifications to the building's existing electrical distribution system.

    Q: Won’t City insurance cover the asbestos abatement or replacement of the HVAC system and air duct system?
    A: Insurance policies do not usually cover asbestos-related issues. In this specific case, the City’s insurance provider, Washington Cities Insurance Authority, specifically excludes claims arising out of or resulting from:

    The use of asbestos in constructing any good, product or structure; or,

    The removal of asbestos from any good, product or structure; or,

    The manufacture, sale, transportation, storage or disposal of asbestos or goods or products containing asbestos.

    This exclusion is not unique to the City’s coverage. The Washington Cities Insurance Authority provides insurance to many Washington cities.

    Q: City staff discovered the presence of asbestos in April. Why is this process taking so long?
    A: Unfortunately, the asbestos contamination at City Hall is complex and cannot be easily identified or abated.

    Initial testing, performed by an asbestos abatement contractor, focused on air quality throughout the building and identifying other asbestos-containing materials after the initial discovery of the broken floor tiles and adhesive. Following the initial testing, the City hired PBS Engineering and Environmental to advise staff, conduct more intensive testing, including air sampling, settled dust sampling, and bulk asbestos sampling.

    Building conditions and limited accessibility to some areas and components of the mechanical systems of City Hall made a comprehensive survey of the HVAC system difficult and time-consuming. Field analysis found that many of the oldest ducts are encapsulated behind heavy plastic sheeting and fiberglass batt insulation and/or multiple layers of ceiling material. Accessing these areas for testing requires coordinated and costly deconstruction of multiple building systems including electrical, data, and low-voltage cabling, plumbing, ceiling grid, and insulation.

    In conjunction with the targeted HVAC testing, a building-wide “Good Faith Inspection” was conducted on June 27, 2023, to detect, identify, and catalog any unknown asbestos-containing materials. The goal of the inspection was a full-building analysis, but the scope of the investigation was also limited due to the inaccessibility of much of the attic and roof structure of the building.

    Q: Why weren’t the staff aware that City Hall had disturbed asbestos?
    A: City Hall was built in 1957 and has been repaired, renovated, and changed owners during its lifetime. The building contains many different construction materials from differing decades – it’s possible that the asbestos contamination within the HVAC system occurred prior to City ownership or during a renovation project in the late 1980s through early 1990s. It is unlikely that the basement floor tiles are the sole source of the asbestos found in the HVAC system.

    Q: Where have City staff been working since City Hall was closed in April?
    A: The displacement of staff from City Hall has been challenging for City teams across all departments and workgroups. Many City administrative functions can be performed remotely, and those work teams have been working from home, from modified/shared workspaces in administrative areas of the Community Center, the Maintenance Building, and the Luther Burbank Administrative Building. Other functions such as Police Operations and Municipal Court require specialized facilities that are not easily replicated, and re-housing these services is the top priority.

    Since June 2023, the Municipal Court has been utilizing City of Kirkland facilities for court days, and working from a conference room at the fire station on other work days. The Kirkland facility does not have enough capacity to house our staff and files, so another solution is needed. At the October 17, 2023 City Council meeting, the Council will review and consider an agenda bill approving an Interlocal Agreement and lease with the City of Newcastle to house Municipal Court operations. After an exhaustive search for temporary leased space, the City Manager is recommending leasing Newcastle Council Chambers for court proceedings and available office space in the Newcastle City Hall building for court staff offices.

    Staff are also working to address the impacts to the Police Department and are in the process of implementing a plan to place temporary modular facilities in the City Hall parking lot for short-term support of police operations. Staff will brief the City Council on the work to re-house the Police Department at a future City Council meeting.

    City staff remain hard at work and most public services continue to be available as normal. More than 80% of City employees are working and delivering services on Mercer Island daily. For information about how to reach City staff or about specific City services, please click here.

    Moving City Hall to Another Facility

    Q: The Mercer Island Community and Event Center (MICEC) is a large facility. Why can’t the City Hall staff and police relocate there?
    A: City staff have identified critical operations that can be performed from the Community Center, including shared workspaces for displaced City staff, and soon, the location of City Council meetings and the Emergency Operations Center (EOC). However, staff remain mindful of the need to preserve the use of the Community Center for existing programming that serves the community and generates crucial revenue for the facility. The Community Center would not be a suitable long-term solution due to the many programs and services the facility provides for the community.

    Q: Can City Hall staff relocate to the Community Center Annex Building?

    A: The Annex Building houses a daycare provider, who holds a current lease for the space. This building is included in the City’s Long Range Facilities Plan project and options for its future use will be evaluated as work progresses.

    Q: What about the Tully’s building? Can City Hall staff or Police move into that space, since the City owns it?
    A: The City has engaged architecture firm Northwest Studio to conduct facility conditions assessments at several City facilities, including the former Tully’s building. In its current condition, the former Tully’s building it is not suitable for occupancy and cannot be used to mitigate the impacts of the City Hall closure.

    The City Council was scheduled to discuss the future use of the former Tully’s property this fall, but the closure of City Hall has led to reprioritization of many work items. It is anticipated the City Council will discuss the future use of this property sometime in 2024.

    Q: Why hasn’t the City rented a different building or space on Mercer Island for City Hall?

    A: The City’s project team is conducting an exhaustive search for alternative facilities on Mercer Island to address the closure of City Hall. The search is challenging, however, as the City has unique functions like Police and Municipal Court that require specialized facilities to meet safety, security, and public access requirements. Unfortunately, there are few spaces on Mercer Island suitable to meet these needs. In addition, the cost of leasing space and anticipated tenant improvements to house the City’s specialized operations must be carefully considered.

    Long-Term Facility Planning

    Q: Many of the City’s facilities are aging, what is the plan to replace them?
    A: Its true that other City facilities, in addition to City Hall, are aging and in need of renovations, safety upgrades, and various other improvements to meet current standards. In early 2023, the City began working on Facilities Conditions Assessments to guide future investment decisions for City facilities and the development of a Long-Range Facilities Plan. These assessments include Mercer Island City Hall, the Public Works Building, the Mercer Island Community and Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop building, and the former Tully’s Building. A second phase will include Facility Conditions Assessments for Fire Station 91, Fire Station 92, and the Mercer Island Community and Event Center.

    The assessments will be used to prioritize a comprehensive plan to maintain, repair or replace these buildings to ensure City facilities can deliver municipal programs and services for the next 50 years.

    Q: Has the City considered selling the City Hall property? What about relocating to Town Center?

    A: The City will consider a wide range of options that will result in a responsible, efficient, and sustainable future for City Hall operations. Northwest Studio and Heartland, the City’s Real Estate Broker, will be assisting the City in evaluating these options. Community engagement on the long-term options to replace City Hall is anticipated in 2024.

    Accessing City Services

    Q: Are City staff available? How do I answer questions or access services?
    A: As always, for the quickest and fastest service, community members should contact the City of Mercer Island Customer Service Team. The City’s Customer Service Team can help answer your questions about services, such as service requests, pet licensing, business licenses, or parking permits during the closure of City Hall. The Customer Service Team can also assist you in getting connected to other teams as needed. They can be reached at 206-275-7600 or at customerservice@mercerisland.gov and are available Monday - Friday from 8:30am - 5:00pm, except for City-observed holidays.

    Q: I need to get a permit for my project. How can I do that with City Hall closed?
    A: Permitting services are available online and permit staff can be reached remotely. This page answers most questions about types of permits and how to obtain them: Permit FAQ | Mercer Island, Washington.

    You may also contact the Community Planning and Development department at 206-275-7605 or epermit.tech@mercerisland.gov.

    Q: I need to make a payment. How can I take care of that while City Hall is closed?
    A: There are multiple options for remitting payment for City bills:

    Mercer Island Utility Bills:

    1. Pay your utility bill online using Visa, MasterCard, Discover, or by electronic check from your bank account (checking or savings). You can also elect to receive paperless bills via e-mail. If you have detailed questions, please see Frequently Asked Questions below.

    1. Drop your bill off in the white payment box in the Mercer Island City Hall parking lot (9611 SE 36th Street, Mercer Island, WA 98040).

    1. Pay your utility bill by mail by sending a check or money order to Mercer Island City Hall, 9611 SE 36th Street, Mercer Island, WA 98040). Please include your account number on the check.

    1. Pay by Phone is now available for utility bills. Make a payment (credit card or e-check) by phone or check your account balance 24/7 with our automated phone service. Have your account number ready and call 855-844-0085.

    Permit Fees:

    1. Via the payment portal (Invoice Cloud) link listed in your invoice or communication from our Permit Services Team.

    1. Drop your check payment off in the white payment box in the Mercer Island City Hall parking lot (9611 SE 36th Street, Mercer Island, WA 98040). Please indicate your permit # on the check.

    Parking Permits:

    1. Mail your completed application and payment to Mercer Island City Hall, 9611 SE 36th Street, Mercer Island, WA 98040). Permits will be sent via return mail after processing.

    1. Drop your bill off in the white payment box in the Mercer Island City Hall parking lot (9611 SE 36th Street, Mercer Island, WA 98040). Permits will be sent via return mail after processing.

    Pet Licenses:

    The City’s Customer Service Team can help answer most of your questions about payment options and various licensing services during the closure and relocation of City Hall. The Customer Service Team can be reached at 206-275-7600 or at customerservice@mercerisland.gov. Monday - Friday from 8:30am - 5:00pm, except for City-observed holidays.

    Q: How do I contact the Municipal Court?
    A: All payments and filings must be sent to the Mercer Island Municipal Court mailing address at 9611 SE 36th St. Mercer Island, WA 98040. The secure drop-box located in the parking lot of City Hall can also be utilized to drop-off payments.

    For any questions or further information please contact your attorney. If you are not represented, contact the Court at 206-275-7604 or court@mercerisland.gov. Court hours are Monday - Thursday 9:00am - 4:00pm.

    For all tickets and court cases that were issued before January 1, 2005 you must contact the King County District Court, East Division at 206-205-9200.

    Q: I want to participate in City Council meetings. How do I do that with City Hall closed?

    A: With the closure of City Hall and Council Chambers in April, the City Council returned to virtual meetings conducted online via Zoom and available to watch live on the City’s YouTube Channel (www.youtube.com/MercerIslandCouncil), and the City’s TV channel (MI-TV 21), as well as listening over the phone. The Mercer Island Community and Event Center (MICEC) has a meeting room available for anyone wishing to make public comment during the appearances portion of the meeting or to watch the meeting on screen.

    Given the long-term nature of the City Hall closure, City staff are in the process of converting the Slater Room at the Mercer Island Community and Event Center into a Council Chambers. Staff anticipate the room will be operational and meetings will return to in-person status in late 2023.

Page last updated: 06 Mar 2024, 01:24 PM