Long-Range Facility Planning/City Hall Closure
Project Overview
In early 2023, the City of Mercer Island began working on Facilities Conditions Assessments to guide future investment decisions for City facilities and the development of a Long-Range Facilities Plan. These assessments include Mercer Island City Hall, the Public Works Building, the Mercer Island Community and Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop building, and the former Tully’s Building. A second phase will include Facility Conditions Assessments for Fire Station 91, Fire Station 92, and the Mercer Island Community and Event Center.
The assessments will be used to prioritize a comprehensive plan to maintain, repair or replace these buildings to ensure City facilities can deliver municipal programs and services for the next 50 years.
City Hall Closure – April 2023
In April 2023, and in the midst of beginning the Facilities Conditions Assessments, staff visually identified broken floor tiles and flooring adhesive in the basement mechanical room at City Hall. Immediate testing of the materials confirmed that both the tiles and the adhesive were asbestos containing materials. This mechanical room houses one of the building's two primary air handling units, a key component of the heating, ventilation, and air conditioning (HVAC) system. To ensure the safety of City staff and visitors, City Hall was immediately closed while further testing was conducted to determine if asbestos fibers were present in other areas of the facility.
The City hired PBS Engineering and Environmental (PBS) to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing. Testing has resulted in asbestos detection in several locations in the building, including in the HVAC system. No airborne asbestos was detected during air quality tests.
City staff and outside experts worked extensively to identify solutions to address the asbestos contamination and evaluate the best path forward for City Hall. Two scenarios for re-occupying the City Hall building, either fully or partially, were evaluated for timeline, preliminary costs, and impact to City operations. Unfortunately, the cost of both scenarios to re-occupy City Hall exceeded the benefits due to the age and condition of the building.
Islanders are encouraged to stay informed and engaged with the facilities planning process here on Let’s Talk. You can review the Frequently Asked Questions, which includes more information about this project and the closure of City Hall, and submit questions for a response using the Ask a Question feature.
Project Overview
In early 2023, the City of Mercer Island began working on Facilities Conditions Assessments to guide future investment decisions for City facilities and the development of a Long-Range Facilities Plan. These assessments include Mercer Island City Hall, the Public Works Building, the Mercer Island Community and Event Center Annex Building, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop building, and the former Tully’s Building. A second phase will include Facility Conditions Assessments for Fire Station 91, Fire Station 92, and the Mercer Island Community and Event Center.
The assessments will be used to prioritize a comprehensive plan to maintain, repair or replace these buildings to ensure City facilities can deliver municipal programs and services for the next 50 years.
City Hall Closure – April 2023
In April 2023, and in the midst of beginning the Facilities Conditions Assessments, staff visually identified broken floor tiles and flooring adhesive in the basement mechanical room at City Hall. Immediate testing of the materials confirmed that both the tiles and the adhesive were asbestos containing materials. This mechanical room houses one of the building's two primary air handling units, a key component of the heating, ventilation, and air conditioning (HVAC) system. To ensure the safety of City staff and visitors, City Hall was immediately closed while further testing was conducted to determine if asbestos fibers were present in other areas of the facility.
The City hired PBS Engineering and Environmental (PBS) to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing. Testing has resulted in asbestos detection in several locations in the building, including in the HVAC system. No airborne asbestos was detected during air quality tests.
City staff and outside experts worked extensively to identify solutions to address the asbestos contamination and evaluate the best path forward for City Hall. Two scenarios for re-occupying the City Hall building, either fully or partially, were evaluated for timeline, preliminary costs, and impact to City operations. Unfortunately, the cost of both scenarios to re-occupy City Hall exceeded the benefits due to the age and condition of the building.
Islanders are encouraged to stay informed and engaged with the facilities planning process here on Let’s Talk. You can review the Frequently Asked Questions, which includes more information about this project and the closure of City Hall, and submit questions for a response using the Ask a Question feature.
-
Public Safety and Maintenance Building Design Progress Update
Share Public Safety and Maintenance Building Design Progress Update on Facebook Share Public Safety and Maintenance Building Design Progress Update on Twitter Share Public Safety and Maintenance Building Design Progress Update on Linkedin Email Public Safety and Maintenance Building Design Progress Update linkAt the May 21, 2024 City Council meeting, City staff presented an update to the Public Safety and Maintenance Building design process.
At the March 1 Planning Session, City Council directed the City Manager to begin planning for a new Public Safety and Maintenance Building (PSM) on the current City Hall Campus (see AB 6420). This new facility will replace the existing Public Works Building and provide a new combined home for the City’s Public Works teams, Police Department, Emergency Operations Center, and IT & GIS.
Staff and the City’s architectural consultant team, Northwest Studio, have conducted workshops with the staff teams expected to be housed in the future PSM building to inform the ongoing design work. The pre-design work considers the spaces needed in the building, in addition to how the spaces are best organized to achieve efficient workflows, to plan for future growth, and to accommodate changing space needs over time.
The presentation also included an overview of Risk Category levels in building design. The risk category of a building reflects the relative resilience to natural disasters and other building failure risks. The new PSM building is intended to be a Level IV Risk Category Building. Risk Category IV includes buildings that are essential in that their continuous use is needed, particularly in response to disasters. Police stations and emergency vehicle garages, Emergency Operations Centers, public works staff areas, and equipment necessary for emergency response, must remain operational during and after major disaster type events.
The presentation concluded with a commitment to continue the work with Police, Public Works, EOC staff, and IT & GIS to gather feedback on design concepts and proposed building programming and workflow. City staff are preparing to return to the City Council in June to present preliminary design and siting concepts for the Public Safety and Maintenance building, including early cost estimates.
-
Presentation to City Council: Follow Up to Public Works Building FCA
Share Presentation to City Council: Follow Up to Public Works Building FCA on Facebook Share Presentation to City Council: Follow Up to Public Works Building FCA on Twitter Share Presentation to City Council: Follow Up to Public Works Building FCA on Linkedin Email Presentation to City Council: Follow Up to Public Works Building FCA linkOn May 21, 2024, City staff presented the City Council with a follow-up to the Facilities Conditions Assessment and related studies of the Public Works building.
At the February 6, 2024 City Council meeting, City staff presented initial findings from the FCA and a high-level overview of the potential repairs and investments necessary to keep the Public Works building operational (see AB 6402). These include both critical systems repairs and basic safety, efficiency, and comfort centered upgrades. At the May 21, 2024 City Council meeting, City staff finalized the FCA report and presented initial findings from a detailed seismic analysis of the building.
While the results of these studies confirm the functional obsolescence of the existing Public Works building, it remains necessary to operate the facility for approximately five years while a new building and yard is designed, funding is secured for construction, and the project is completed. Near-term issues that will be addressed include:
- Completely remove the existing green roof and accumulated soil.
- Install anchoring between the walls and the wood diaphragms at the two higher level roofs (the second-floor office space and high bay garage).
- Install a subsurface concrete-grade beam along the exterior at each end of the high-bay garage doors.
- Retrofit numerous unbraced interior CMU (concrete masonry unit) walls throughout the building.
- Provide additional fire extinguishers or extinguishing systems throughout the building.
- Include fall restraint guards at the Public Works building and select outbuildings.
- Apply safety film to existing wired glass windows to prevent shattering.
City staff have started to address the priorities identified in the report to extend the useful life of the Public Works Building. Funding recommendations for the identified capital projects will be included for consideration this fall as part of the Biennial Budget Development process.
If occupancy of the Public Works building is anticipated to exceed five years, the next set of investments will be significant. Construction costs are expected to increase, and upgrades to meet current code requirements will become necessary, further expanding the cost of operating this facility at a minimally functional level.
You can view the discussion and review the presentation here.
-
A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building
Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Facebook Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Twitter Share A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building on Linkedin Email A Message to the Community from the Mercer Island City Council Regarding Planning for the Development of a Replacement Public Safety and Maintenance Building linkLast week, your City Council took a pivotal step in the future of City operations by unanimously approving the costing and design for a new Public Safety and Maintenance Building on the current City Hall campus. This facility would house the City’s Police Department and public works crews, providing a safe and functional facility that meets the urgent needs of our City today.
The motion, put forward by Deputy Mayor Rosenbaum during the Council's annual planning session, demonstrates a collective commitment to enhancing the safety and well-being of our employees and community. The existing Public Works Building is well beyond its useful life and hasn’t met our needs for some time. The closure of City Hall only exacerbated this challenge, displacing staff across all teams and the specialized functions of our Police Department.
Careful evaluation and planning brought us to this path forward. Building a new facility serving both our police and public works teams meets the unique needs of both departments in a much more efficient manner. The City Manager will now commence planning for this new facility, with a preliminary scope and cost estimate due in Q2 2024.
What does this mean for a future City Hall and the rest of the City’s teams? We continue to discuss opportunities for a home in Town Center – a shift that represents a generational investment in a more accessible, efficient, and community-focused downtown City Hall. These decisions are not just about buildings and staffing but about laying the groundwork for a more connected, safe, and vibrant Mercer Island. We’ll continue to keep you updated on Let’s Talk, the City’s public engagement platform.
The success of last week’s Council Planning Session reflects extensive preparation by City staff and the Council's supportive and collaborative spirit aimed at recognizing the valuable contributions of all City employees. Together, we are able to navigate the complexities of our current challenges and make informed decisions that reflect the priorities and needs of you, our residents.
A great deal of dedication, insightful discussions, and strategic decisions have set in motion what we believe will be a very positive trajectory for the City of Mercer Island. These initiatives will bring about meaningful and positive changes in our community – we look forward to working across the Island to articulate this vision and we’re excited to see the impact our collective efforts will have for the Island’s future.
Mercer Island City Council
Mayor Salim Nice
Deputy Mayor Dave Rosenbaum
Councilmember Lisa Anderl
Councilmember Jake Jacobson
Councilmember Craig Reynolds
Councilmember Wendy Weiker
Councilmember Ted Weinberg -
Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building
Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Facebook Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Twitter Share Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building on Linkedin Email Council Directs City Manager to Commence Planning for a New Public Safety and Maintenance Building linkAt the City Council Planning Session on March 1, 2024, the Council unanimously approved AB 6420 directing the City Manager to commence planning for a new Public Safety and Maintenance Building on the current City Hall campus. This new facility will replace the existing Public Works Building and provide a new combined home for the City’s Public Works teams and Police Department.
A preliminary scope and cost estimate will be presented to the Council in Q2 2024.
In early 2023, the City began a process to complete Facility Conditions Assessments (FCAs) for various municipal buildings, including City Hall, the Public Works Building, the Annex Building at the Mercer Island Community & Event Center, the Luther Burbank Administrative Building, the Mercer Island Thrift Shop, and the former Tully’s Building. Due to the emergency closure of City Hall in April 2023, this work was reprioritized to meet the most pressing needs.
Given the age and condition of the Public Works Building, the City Manager directed staff and consultants to complete a FCA for this building, while pausing assessment work on the other buildings.
The assessment identified multiple systems that are failing or in need of significant repair or investment. This information was presented to the City Council on February 6, 2024 (AB 6402).
Combined with the City’s urgent space needs for teams displaced by the City Hall closure, the City Manager recommended that the Council prioritize the Public Works Building for replacement. Council’s direction allows the City Manager to proceed with building this new facility on the existing campus.
More information about this project will be shared soon. You can review the full Let’s Talk page to learn more about the City’s Long Range Facility Planning work.
-
Council to Review Town Center Commuter Parking Site Concept
Share Council to Review Town Center Commuter Parking Site Concept on Facebook Share Council to Review Town Center Commuter Parking Site Concept on Twitter Share Council to Review Town Center Commuter Parking Site Concept on Linkedin Email Council to Review Town Center Commuter Parking Site Concept linkIn 2017, the City entered into a settlement agreement with Sound Transit to offset local impacts of the East Link light rail project. As part of this agreement, $4.41 million was dedicated for long term regional transit commuter parking projects near the new Light Rail Station in Town Center.
At the February 20 regular meeting, the City Council will review a recommendation and preferred site concept for a commuter parking project in the Town Center, presented by City Manager Jessi Bon. The Commuter Parking Project site consists of three different parcels, including the former Tully’s Property, acquired and assembled over multiple years for the purpose of providing long-term regional transit commuter parking.
You can attend the February 20 council meeting in-person or virtually to watch the discussion.
-
Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment
Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Facebook Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Twitter Share Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment on Linkedin Email Council to Review Preliminary Findings from Public Works Building Facility Conditions Assessment linkAs part of the process to evaluate the condition of municipal buildings and develop a plan for their future, the City Council will review preliminary findings from the Public Works Building Facility Conditions Assessment at the February 6, 2024 regular meeting. Staff and consultants will present the preliminary findings from the assessment and answer councilmember questions.
The Public Works building, located behind City Hall, was constructed primarily as a workshop and mechanic facility in 1981. Since then, it's been repurposed several times to meet the changing needs of City operations. The building is 15,350 square feet and currently houses the following operational and administrative teams made up of Full Time Equivalent Employees (FTEs) and Limited Term Employees (LTEs):
- Right-of-Way and Stormwater Team (10 FTEs)
- Water Utility (8.5 FTEs, 3 LTEs)
- Sewer Utility (6.5 FTEs)
- Parks Maintenance (10 FTEs)
- Support Services Team (3 FTEs, 1 LTE)
- Public Works Engineering and Administration Teams (19 FTEs)
Following the closure of City Hall in April 2023, the City’s Utility Billing Team was also re-located at the Public Works Building (3 FTEs). In total, there are 64 employees (FTE and LTE equivalents) and 15 to 20 seasonal employees who currently operate out of this facility.
The Facility Conditions Assessment process identified the following preliminary findings about the building's condition:
- Roofing is at the end of its projected useful life and leaks are prevalent throughout the building.
- The current 150kVA electrical service is insufficient to support the current needs of the facility.
- The electrical distribution system is aged, with some critical components at the end-of-life.
- The original HVAC system is mostly obsolete throughout the building, delivering poor performance, high energy consumption, and marginal air quality.
- Plumbing is inadequate to meet the staffing levels for the building, requiring the use of portable toilets to meet sanitation requirements.
Based on the findings from the FCA and known operational deficiencies, the City Manager is recommending the Public Works Building be prioritized for replacement. Staff and consultants are currently working on preliminary replacement strategies for the City Hall Building and the recommendation is to combine the planning process to address replacement of both buildings.
While the initial assessment is preliminary, staff and consultants are finalizing the assessment and cost estimates - they expect to have this work complete by June 2024. Staff will identify critical system repairs needed to extend the life of the building temporarily (for five to ten years) while replacement strategies are developed. Staff will present those strategies to the City Council as part of the upcoming 2025-2026 Biennial Budget Development process.
A follow-up discussion on City facilities is planned for the March 1, 2024, City Council Planning Session. This presentation and discussion will primarily focus on the replacement strategies for City Hall and the Public Works Building.
You can review the City Council Agenda Bill 6402 for additional details on this presentation. The preliminary report is also available online.
-
An Update on City Operations, Planning Continues for City Hall
Share An Update on City Operations, Planning Continues for City Hall on Facebook Share An Update on City Operations, Planning Continues for City Hall on Twitter Share An Update on City Operations, Planning Continues for City Hall on Linkedin Email An Update on City Operations, Planning Continues for City Hall linkEarlier this year, the City Council voted to permanently close City Hall. City staff, the City Council, and outside experts have since been hard at work planning for a solution to the City Hall closure, as part of the City’s existing Long Range Facility Planning process.
While City Hall may be closed, most City operations continue as normal. Approximately 80% of City employees continue to work in-person on Mercer Island, whether from shared workspaces in administrative areas of the Community Center, the Maintenance Building, the Luther Burbank Administrative Building, or out in the field. Remaining staff are working from a combination of home offices and in shared/rotating office spaces on-Island, often holding meetings at the Community Center or at other locations.
The City is standing up temporary facility solutions for specialized operations that were displaced by the closure of City Hall, including City Court and Police Department facilities:
Municipal Court: At the November 7 City Council meeting, the Council approved a lease agreement with the City of Newcastle allowing Mercer Island Municipal Court to temporarily operate out of Newcastle City Hall. Court staff are currently arranging operating details, with information on accessing court services in Newcastle coming soon.
Police Department: While our Police Department staff have worked hard to continue normal levels of service without access to the Police wing of City Hall, day-to-day operations have been challenging for our officers. At the November 21 City Council meeting, the Council reviewed a budget allocation for Police Department portable facility solutions. These temporary facilities will provide dedicated spaces for the many specialized needs of a police department and greatly ease day-to-day challenges for our officers and staff.
Work on a long-term replacement strategy for City Hall continues. The City will consider a wide range of options that will result in a responsible, efficient, and sustainable future for City Hall operations. While much of the planning related to real estate transactions must be conducted confidentially through the City’s broker, community engagement on the long-term options to replace City Hall is anticipated in 2024. Islanders are encouraged to stay updated and engaged with this project here on Let’s Talk.
As always, City staff remain available and ready to assist you. For the quickest and fastest service, community members should contact the City of Mercer Island Customer Service Team at 206-275-7600 or at customerservice@mercerisland.gov.
-
A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall
Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Facebook Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Twitter Share A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall on Linkedin Email A Letter from City Manager Jessi Bon on the Permanent Closure of City Hall linkOctober 4, 2023
For the past six months, my office – alongside a team of staff and outside experts – have been working to address the unexpected closure of City Hall due to the discovery of asbestos in the building’s HVAC system. At last night’s City Council meeting, the Council unanimously supported my recommendation to permanently close City Hall. I want to provide an update on why that decision was made and what’s ahead.
In April of this year, maintenance staff identified broken floor tiles in the City Hall basement mechanical room and these tiles were confirmed to contain asbestos. Because this mechanical room houses key components of the building’s HVAC system, including an air handling unit, City Hall was immediately closed while further testing was conducted.
From April through July, the City worked with PBS Engineering and Environmental to conduct comprehensive asbestos testing of the City Hall building, which included air sample, settled dust, and bulk material testing, with a focus on the HVAC system. Fortunately, no asbestos fibers were identified in any air samples, but settled dust tests did confirm asbestos is present above background levels (which requires abatement) in several segments of the HVAC system. Based on these findings, the HVAC system was turned off and has been inoperable since mid-May.
The location of both confirmed and likely asbestos in the City Hall HVAC system makes abatement extremely difficult, costly, and time-consuming. There is limited accessibility to some areas of the HVAC system, as many of the oldest ducts are encapsulated behind heavy plastic sheeting, fiberglass batt insulation, and/or multiple layers of ceiling material. The testing inside the HVAC system was taken as far as it could but was halted in early summer due to limited access to the remaining areas of the system. The presence of fiberglass batt insulation throughout the system also means it is not possible to clean and return the existing system to operation. The only option to address the HVAC asbestos contamination is a full replacement of the system, and subsequently, the associated infrastructure (ceiling, lighting, cabling, etc.).
City staff and consultants provided a comprehensive report to the City Council on these findings at the July 18, 2023, City Council meeting and that information is available here on Let’s Talk.
With that information in hand, we evaluated different scenarios for re-occupying City Hall, either fully or partially. The preliminary cost estimate to re-occupy City Hall is in excess of $10 million, with an estimated timeline of nearly two years to complete the work. We also considered a more modest approach and evaluated re-occupancy of the police portion of the building only, and those cost estimates are in excess of $4 million. While these costs alone likely exceed the anticipated return on investment, there are other factors that were considered in the decision to permanently close City Hall.
City Hall was built in 1957 and has been repaired and renovated over the years, with the last major renovation occurring in the late 1980s. Prior to the asbestos situation, the City Council recognized the need for a replacement strategy for this building, and in early 2023, the City began working on a Facilities Conditions Assessment to guide long-term decisions. The initial assessment work highlighted the many other matters of concern related to the long-term use of City Hall. The building suffers from structural and seismic deficiencies. Almost all the interior walls have been identified as lacking lateral bracing and, unless reinforced, are at risk of failure in the event of seismic activity, potentially rendering the building inoperable. Additionally, the building does not conform with current energy or building code requirements, and multiple building systems are failing or need to be substantially replaced.
Given this additional information and the anticipated investment needed to re-occupy City Hall and bring it up to current standards, the decision was made to permanently close the building and turn our attention to identifying a replacement strategy.
What does this mean for City services in the short-term? While we’re still working through our day-to-day operations, I can tell you that City staff remain hard at work and almost all public services continue to be available as normal. I’m incredibly grateful to our staff teams for their flexibility and creativity as we’ve figured out how to double up in offices, move equipment to other buildings, and sort through this challenge. Approximately 80% of our team continues to work in-person on Mercer Island, whether from shared workspaces in administrative areas of the Community Center, the Maintenance Building, the Luther Burbank Administrative Building, or out in the field. The remaining staff are working from a combination of home offices and in shared/rotating office spaces on-Island, often holding meetings at the Community Center or at other locations.
We encourage all Islanders to review our Let’s Talk Page – you can learn more about the many details involved in the decision to close City Hall and ask a question that hasn’t yet been answered. As always, our Customer Service Team stands ready to assist you in answering questions or accessing City services.
While having to suddenly close City Hall was unexpected and unfortunate, we are turning our attention to the critical work involved in identifying a long-term replacement strategy and discussions with the community and the City Council are anticipated to begin in 2024.
Thank you,
Jessi Bon
Mercer Island City Manager -
October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall
Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Facebook Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Twitter Share October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall on Linkedin Email October 3, 2023 – City Council to Consider Resolution Permanently Closing City Hall linkAt the October 3, 2023, City Council meeting, City Manager Jessi Bon will recommend that the City cease operations at Mercer Island City Hall and permanently close the building (see Resolution No. 1650). This recommendation is due to the discovery of asbestos containing materials, primarily in the City Hall HVAC system, that cannot be easily remediated.
The City Manager has organized specific staff teams to address the many issues and work items related to the closure of City Hall. This includes moving personal items out of City Hall, technology transitions, support for work groups that are the most impacted by the closure including Police and Municipal Court, and other matters.
- At the October 17, 2023 City Council meeting, the Council will review and consider an agenda bill approving an Interlocal Agreement and lease with the City of Newcastle to house Municipal Court operations. After an exhaustive search for temporary leased space, the City Manager is recommending leasing Newcastle Council Chambers for court proceedings and available office space in the Newcastle City Hall building for court staff offices.
- Staff are also working to address the impacts to the Police Department and are in the process of implementing a plan to place temporary modular facilities in the City Hall parking lot for short-term support of police operations. Staff will brief City Council on the work to re-house the Police Department at a future City Council meeting.
- Long-term planning work related to the replacement of City Hall is underway. Discussions with the City Council and the community are planned for 2024.
Staff and consulting teams also continue to work on the logistics of preparing City Hall for permanent closure, including planning for the storage of furniture, equipment, and supplies, managing paper records, discarding unneeded items, and the retrieval of personal items. The HVAC system at City Hall, for example, has been inactive since mid-May and cannot be operated safely. Since the building doesn’t have a functional heating system, water service at City Hall has been shut off and the plumbing system drained to help avoid potential frozen pipes should the region experience an early-fall cold snap.
Stay updated on both current City operations and the planning for a permanent City Hall solution here on Let’s Talk. Islanders are encouraged to review the Frequently Asked Questions below, which includes information on what ideas have been considered and additional details. You can also submit questions for a response using the Ask a Question feature.
-
July 18, 2023 – Update to City Council on City Hall Closure and Next Steps
Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Facebook Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Twitter Share July 18, 2023 – Update to City Council on City Hall Closure and Next Steps on Linkedin Email July 18, 2023 – Update to City Council on City Hall Closure and Next Steps linkAt the July 18, 2023 City Council meeting, representatives from PBS Engineering and Environmental (PBS) provided an overview of the environmental assessment work performed at City Hall and reviewed the findings. Here’s what was presented:
Testing Methods and Results
Following the initial asbestos testing, the City hired PBS to advise staff, conduct more intensive testing, and ensure that industry best practices were followed in further detection and risk mitigation efforts. Between late April and early July, PBS performed three primary types of tests: air quality, settled dust, and bulk material testing, with hundreds of samples collected across all test types.
Air Sampling
The intent of air sampling is to screen interior air for potential asbestos fibers. Air samples were collected from locations throughout the building, using high-volume air sampling pumps and analyzed using the NIOSH 7402 method, which uses Transmission Electron Microscopy (TEM) and reports findings in concentrations of fibers per cm3. No asbestos fibers were identified in the collected air samples.
Settled Dust Sampling
The intent of this sampling is to evaluate surface dust in the building and mechanical system for potential asbestos content. PBS collected settled dust samples at representative locations throughout the interior of City Hall and inside the HVAC system. Each sample was collected using an air sampling pump to draw dust from a 100 cm2 area.
Samples were analyzed using the ASTM D 5575-09 method, which uses Transmission Electron Microscopy (TEM) and reports findings in concentrations of structures per square centimeter (s/cm2). Findings are reported based on the size of any asbestos identified, grouped by between 0.5 and 5 microns, and those larger than 5 microns.
‘Background levels’ of asbestos structures in accumulated dust range from an average of 1,000 s/cm2 in non-industrial areas to 10,000 s/cm2 in cities and industrial areas where asbestos materials are common. Levels above 10,000 s/cm2 are generally considered to be “above background” in any geographical location. There are no regulatory thresholds for the amount of asbestos in surface dust.
Asbestos concentrations in excess of 10,000 s/cm2 were identified in six of the samples, all of which were associated with the HVAC system.
Bulk Asbestos Sampling
PBS took 84 samples from various materials for the presence of asbestos. This has been conducted to confirm asbestos content in select building materials.
Samples were analyzed according to either EPA Method 600R-93/116 using Polarized Light Microscopy (PLM) or EPA Method 600R-93/116 TEM Bulk Semi-Quantitative.
In addition to the various flooring and adhesive materials that tested positive for the presence of asbestos, three bulk samples taken from HVAC filters contained trace amounts of asbestos, and two window-glazing putty samples tested positive.
Limitations on Testing and Inspection
One goal of this wide-ranging testing was to create a comprehensive survey of conditions inside the HVAC system. However, field analysis found that many of the oldest ducts are encapsulated behind heavy plastic sheeting and fiberglass batt insulation and/or multiple layers of ceiling material. Accessing these areas for testing will require coordinated and costly deconstruction of multiple building systems including but not limited to electrical, data and low-voltage cabling, plumbing, ceiling grid, and insulation. The testing inside the HVAC system was taken as far as it could but was halted due to limited access to the remaining areas.
In conjunction with the targeted HVAC testing, a building-wide “Good Faith Inspection” was conducted on June 27, 2023 to detect, identify, and catalog any unknown asbestos-containing materials. The goal of the inspection was a full-building analysis, but the scope of the investigation was also limited due to the inaccessibility of much of the attic and roof structure of the building. No previously unknown asbestos-containing materials were found in the areas that were accessible for surveying.
While the floor tiles and adhesive found in the basement mechanical room alerted staff to the asbestos issue and prompted extensive testing in the building, these items are not likely to be the sole source of asbestos detected in portions of the HVAC system. Additional sources of asbestos contamination have not been definitively identified, and likely will not be uncovered by further testing. Based on the varying levels and locations of asbestos identified through the testing completed to date, PBS consultants believe there is a high probability that one or more sources of contamination contributed to the issue over the life of the building. Further, there is a high likelihood that the original asbestos-containing materials were removed during a previous renovation in the late 1980s.
Abatement
Abatement, which is the removal of contaminated materials and equipment by a specialized contractor, has only been completed in a limited area of the basement of City Hall. Specifically, the basement mechanical room floor with asbestos containing broken tiles and adhesive was abated by a licensed contractor in mid-May, with post-abatement sampling of the floor confirming that there are no longer detectable traces of asbestos present. The HVAC system at City Hall remains unabated and turned off. Unless it is abated, it must remain off.
Potential Solutions to Re-Occupy City Hall
Northwest Studio, the City’s architect team, presented two preliminary scenarios to the City Council to re-occupy City Hall:
The first scenario was a full re-occupancy of City Hall. This work would require abatement of the floor tiles in the basement mechanical room, replacement of the HVAC hydronic and ventilation system, and the replacement of various building infrastructure required by replacement of the HVAC system (ceilings, light fixtures, cabling, etc.). The preliminary cost estimate to re-occupy City Hall under this scenario is $10 million with an estimated timeline of nearly two years to complete the work. This cost estimate does not include full abatement costs or softs costs such as design, engineering, and project management costs.
The second scenario was to investigate the possibility of re-occupying only the Police Department areas of City Hall for seven years while longer-term options were investigated. The team looked at partitioning the existing Police Department spaces from the remainder of the City Hall building, abating those spaces, removing the existing HVAC system, and installing a contemporary system to serve this occupancy. The preliminary cost estimate to abate and re-occupy the Police Department portion of City Hall is over $4 million with an estimated timeline of 12 to 18 months to complete the work. This cost estimate does not include full abatement costs or softs costs such as design, engineering, and project management costs.
Upon learning of the initial cost estimates to abate and re-occupy the City Hall building, and in consideration of the age and condition of the building, Councilmembers indicated during discussions at the July 18, 2023 City Council meeting that the costs to re-occupy City Hall outweighed the benefits of re-opening the building.
Key Dates
-
October → December 2023
-
October 03 2023
-
July 18 2023
-
April → July 2023
-
April 17 2023
Who's Listening
-
City Manager's Office