Updates for April 2025

Progress to replace aging equipment and renovate the play area at First Hill Park continues! Keep reading for an update on equipment delivery, permitting, and expected construction timing.

  • Play equipment delivered New play equipment from Landscape Structures, Inc., was delivered in February and is being stored at Public Works until construction begins. Pieces include a multi-level tower structure with two slides; a two-swing bay of traditional belt swings; and nature-themed steppers, seats, and a tunnel.
  • Permits secured – The City building permit was approved last month, and staff are working with the Community Planning and Development department to finalize the permit issuance.
  • Confirming construction scope and timing This week, City staff, the Berger team, and representatives from PlayCreation will meet on-site to refine the construction scope and project schedule. Staff aim to execute the construction contract in the next several weeks and anticipate construction will take 2-3 months to complete.


Questions? Contact Sarah Bluvas, CIP Project Manager, at sarah.bluvas@mercerisland.gov or 206.549.1032.