Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete!

On July 25, crews reached a major project milestone, completing the structural reinforcement of the building and chimney!

Other work on the project continued including:

  • Reinstalling the parapet capstones along the perimeter of the roof.
  • Painting the restrooms.
  • Forming and pouring a new concrete countertop for the concession stand.
  • Installing the new 400-amp power supply on the north wall of the building
  • Installation of new plumbing fixtures.
  • Installation of new outside light fixtures.
  • Applying an anti-graffiti coating to the brick exterior.

Check out our photo library for pictures of the progress!

Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on Facebook Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on Twitter Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on Linkedin Email Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! link