Luther Burbank Dock and Waterfront Renovations
The City is completing a years-long process to renovate the Luther Burbank Park waterfront. Built in 1974, the dock structures and adjacent waterfront have reached their useful life and need significant repairs to continue providing the public access to shoreline recreation.
Work to develop this project began in 2019, and the design is informed by the Luther Burbank Park Master Plan, which envisions the park's waterfront as a hub for small motorized and hand-powered watercraft activities. The project also considers accessibility and aesthetic improvements for a comprehensive site plan that, once executed, will expand access to Lake Washington for a variety of park visitors.
In 2024, the City completed seismic retrofits and other improvements to the Boiler Building and restroom/concession stand annex. Now preparations are underway to renovate the dock structures, North Beach, and waterfront plaza.
Construction of the next phase of improvements is anticipated to begin in fall 2026 and includes:
- Renovating the north pier, including replacing decking, jacketing creosote-timber piles, and repairing/replacing degrading piles to continue providing moorage access for large, motorized vessels (26’ and above).
- Replacing the central and south dock structures with a new wave attenuator/mooring float to serve small and mid-sized motorized vessels (below 26’) and special purpose float to serve non-motorized watercraft, including adding an ADA-accessible kayak launch.
- Installing a new ADA overwater platform off the plaza bulkhead to provide a stable surface where community members can enjoy shoreline activities and “get their feet wet.”
- Renovating the North Beach to provide ADA access to the water, including installing a new concrete pathway from the north bulkhead, installing an ADA beach mat to the water, and replacing non-native vegetation with new riparian and native plantings.
- Adding ADA pathway connections from the South Shoreline Trail and renovating the existing hidden path from the plaza to the playground with an ADA switchback trail and concrete stairs.
- Enhancing shoreline ecological functions with habitat gravel and lakebed cleanup.
- Upgrading sewer, electrical, stormwater, and irrigation utilities as well as installing a new fire suppression system to serve the docks and Boiler Building.
- Installing a new raw water intake system to enable the City to activate its water rights and draw water from Lake Washington to support park irrigation.
- Installing plaza improvements and amenities, including new surfacing, picnic tables/benches, signage, and the Mercer Island Medallions public art project.
Staff anticipate that construction will take 15 to 18 months to complete. Regular updates will be shared on Let's Talk once work begins, including information about park closures and impacts.
This project is funded in part by the Washington State Recreation and Conservation Funding Board, the U.S. Department of Fish and Wildlife, and the King County Flood Control District. The Washington State Department of Natural Resources leases the shorelands at no cost for public access to the waters of the State.
The City is completing a years-long process to renovate the Luther Burbank Park waterfront. Built in 1974, the dock structures and adjacent waterfront have reached their useful life and need significant repairs to continue providing the public access to shoreline recreation.
Work to develop this project began in 2019, and the design is informed by the Luther Burbank Park Master Plan, which envisions the park's waterfront as a hub for small motorized and hand-powered watercraft activities. The project also considers accessibility and aesthetic improvements for a comprehensive site plan that, once executed, will expand access to Lake Washington for a variety of park visitors.
In 2024, the City completed seismic retrofits and other improvements to the Boiler Building and restroom/concession stand annex. Now preparations are underway to renovate the dock structures, North Beach, and waterfront plaza.
Construction of the next phase of improvements is anticipated to begin in fall 2026 and includes:
- Renovating the north pier, including replacing decking, jacketing creosote-timber piles, and repairing/replacing degrading piles to continue providing moorage access for large, motorized vessels (26’ and above).
- Replacing the central and south dock structures with a new wave attenuator/mooring float to serve small and mid-sized motorized vessels (below 26’) and special purpose float to serve non-motorized watercraft, including adding an ADA-accessible kayak launch.
- Installing a new ADA overwater platform off the plaza bulkhead to provide a stable surface where community members can enjoy shoreline activities and “get their feet wet.”
- Renovating the North Beach to provide ADA access to the water, including installing a new concrete pathway from the north bulkhead, installing an ADA beach mat to the water, and replacing non-native vegetation with new riparian and native plantings.
- Adding ADA pathway connections from the South Shoreline Trail and renovating the existing hidden path from the plaza to the playground with an ADA switchback trail and concrete stairs.
- Enhancing shoreline ecological functions with habitat gravel and lakebed cleanup.
- Upgrading sewer, electrical, stormwater, and irrigation utilities as well as installing a new fire suppression system to serve the docks and Boiler Building.
- Installing a new raw water intake system to enable the City to activate its water rights and draw water from Lake Washington to support park irrigation.
- Installing plaza improvements and amenities, including new surfacing, picnic tables/benches, signage, and the Mercer Island Medallions public art project.
Staff anticipate that construction will take 15 to 18 months to complete. Regular updates will be shared on Let's Talk once work begins, including information about park closures and impacts.
This project is funded in part by the Washington State Recreation and Conservation Funding Board, the U.S. Department of Fish and Wildlife, and the King County Flood Control District. The Washington State Department of Natural Resources leases the shorelands at no cost for public access to the waters of the State.
-
Luther Burbank Dock and Waterfront Improvements Construction Bid Award
Share Luther Burbank Dock and Waterfront Improvements Construction Bid Award on Facebook Share Luther Burbank Dock and Waterfront Improvements Construction Bid Award on X (formerly Twitter) Share Luther Burbank Dock and Waterfront Improvements Construction Bid Award on Linkedin Email Luther Burbank Dock and Waterfront Improvements Construction Bid Award linkNext Tuesday, September 1, 2026, the Mercer Island City Council will consider awarding construction of the Luther Burbank Park Dock and Waterfront Improvements Project to Quigg Bros., Inc. (See AB6989). Details for attending the meeting virtually or in-person are available here.
Quigg Bros., Inc., is an Aberdeen-based firm specializing in marine construction. Their recent successfully completed waterfront projects around the state include the Des Moines Marina Redevelopment (2025-2026), the Port of Poulsbo Breakwater Replacement (2022-2024), the Fry Creek Pump Station Replacement for the City of Aberdeen (2022-2024), and multiple Foss Waterways projects for the City of Tacoma.
The total construction contract for the dock and waterfront projects is $6,730,000 (including sales tax). If awarded, construction is anticipated to begin this fall and will take approximately 15 to 18 months.
During construction, a portion of Luther Burbank Park will be closed to support construction activities and ensure public safety. The remainder of the park will remain open to the public throughout construction. Additional information about specific closures and impacts will be shared as construction progresses.
Regular updates will be shared here on Let’s Talk once construction begins. Stay tuned for more!
Next Tuesday, September 1, 2026, the Mercer Island City Council will consider awarding construction of the Luther Burbank Park Dock and Waterfront Improvements Project to Quigg Bros., Inc. (See AB6989). Details for attending the meeting virtually or in-person are available here.
Quigg Bros., Inc., is an Aberdeen-based firm specializing in marine construction. Their recent successfully completed waterfront projects around the state include the Des Moines Marina Redevelopment (2025-2026), the Port of Poulsbo Breakwater Replacement (2022-2024), the Fry Creek Pump Station Replacement for the City of Aberdeen (2022-2024), and multiple Foss Waterways projects for the City of Tacoma.
The total construction contract for the dock and waterfront projects is $6,730,000 (including sales tax). If awarded, construction is anticipated to begin this fall and will take approximately 15 to 18 months.
During construction, a portion of Luther Burbank Park will be closed to support construction activities and ensure public safety. The remainder of the park will remain open to the public throughout construction. Additional information about specific closures and impacts will be shared as construction progresses.
Regular updates will be shared here on Let’s Talk once construction begins. Stay tuned for more!
-
New Self-Guided Tour of Luther Burbank Park!
Share New Self-Guided Tour of Luther Burbank Park! on Facebook Share New Self-Guided Tour of Luther Burbank Park! on X (formerly Twitter) Share New Self-Guided Tour of Luther Burbank Park! on Linkedin Email New Self-Guided Tour of Luther Burbank Park! link
Community members can now take a self-guided tour of some Luther Burbank Park’s rich cultural and natural history via the STQRY app!
What is STQRY?
Pronounced “story,” this is the City’s digital platform for engaging the community with arts, culture, and heritage/history. The Mercer Island Arts Council launched STQRY in 2014, and the app currently features more than 30 entries about works in the public art collection as well as sculptures on view/for sale in the Greta Hackett Outdoor Sculpture Gallery. In 2023, the City started adding entries about Mercer Island history and heritage, including information about Riley Cove at Lincoln Landing.
Take a Tour of Luther Burbank Park
The Phase 1 Renovations completed at the Boiler Building in 2024 were partially funded through the Washington State Historical Society’s Heritage Capital Projects program. As a condition of the grant, the City developed a new interpretive program that highlights the rich history of Luther Burbank Park.
Using the STQRY platform and bronze plaques designed by local artist Marsha Rollinger, visitors can explore stories spanning from the early days of Mercer Island entrepreneur C.C. Calkins to the site’s later use as the Luther Burbank School. Together, these interpretive elements help bring the park’s unique history to life for visitors of all ages.
The tour includes stops at the following locations:
- Boiler Building
- Luther Burbank Park Administrative Building
- Former School Parade Grounds (located near the park flagpole)
- Dairy Barn Ruins
- Calkins Point
Four locations are marked with a bronze plaque designed by Rollinger and fabricated by Two Ravens Studio in Tacoma, WA. (An interpretive sign installed in 2025 denotes the Dairy Barn Ruins stop.)
How do I access the tour?
Community members can access the tour via STQRY in a few ways:
- Search “Explore Mercer Island” to download the free STQRY app in the App Store or Google Play. The tour can be accessed by clicking on the “Luther Burbank Park History Tour” button in the navigation bar on the bottom of the app.
- Visit mercerisland.stqry.app via a desktop or mobile web browser device and click on the “Luther Burbank Park History Tour” button.
- Scan the QR code located on each plaque to go straight to that feature’s STQRY entry.
Many thanks to the Mercer Island Historical Society and Friends of Luther Burbank Park for the collaboration over the last few years to bring this tour to fruition!
Community members can now take a self-guided tour of some Luther Burbank Park’s rich cultural and natural history via the STQRY app!
What is STQRY?
Pronounced “story,” this is the City’s digital platform for engaging the community with arts, culture, and heritage/history. The Mercer Island Arts Council launched STQRY in 2014, and the app currently features more than 30 entries about works in the public art collection as well as sculptures on view/for sale in the Greta Hackett Outdoor Sculpture Gallery. In 2023, the City started adding entries about Mercer Island history and heritage, including information about Riley Cove at Lincoln Landing.
Take a Tour of Luther Burbank Park
The Phase 1 Renovations completed at the Boiler Building in 2024 were partially funded through the Washington State Historical Society’s Heritage Capital Projects program. As a condition of the grant, the City developed a new interpretive program that highlights the rich history of Luther Burbank Park.
Using the STQRY platform and bronze plaques designed by local artist Marsha Rollinger, visitors can explore stories spanning from the early days of Mercer Island entrepreneur C.C. Calkins to the site’s later use as the Luther Burbank School. Together, these interpretive elements help bring the park’s unique history to life for visitors of all ages.
The tour includes stops at the following locations:
- Boiler Building
- Luther Burbank Park Administrative Building
- Former School Parade Grounds (located near the park flagpole)
- Dairy Barn Ruins
- Calkins Point
Four locations are marked with a bronze plaque designed by Rollinger and fabricated by Two Ravens Studio in Tacoma, WA. (An interpretive sign installed in 2025 denotes the Dairy Barn Ruins stop.)
How do I access the tour?
Community members can access the tour via STQRY in a few ways:
- Search “Explore Mercer Island” to download the free STQRY app in the App Store or Google Play. The tour can be accessed by clicking on the “Luther Burbank Park History Tour” button in the navigation bar on the bottom of the app.
- Visit mercerisland.stqry.app via a desktop or mobile web browser device and click on the “Luther Burbank Park History Tour” button.
- Scan the QR code located on each plaque to go straight to that feature’s STQRY entry.
Many thanks to the Mercer Island Historical Society and Friends of Luther Burbank Park for the collaboration over the last few years to bring this tour to fruition!
-
Major Project Milestone Reached for Luther Burbank Park Waterfront!
Share Major Project Milestone Reached for Luther Burbank Park Waterfront! on Facebook Share Major Project Milestone Reached for Luther Burbank Park Waterfront! on X (formerly Twitter) Share Major Project Milestone Reached for Luther Burbank Park Waterfront! on Linkedin Email Major Project Milestone Reached for Luther Burbank Park Waterfront! linkThis week, the City advertised the Luther Burbank Park Waterfront Improvements project for construction, marking a major step forward in completing renovations at the waterfront!
Design for this project began in 2020 and aims to provide universal access to the Luther Burbank waterfront by:
- Renovating/replacing the docks to better serve hand-powered and motorized watercraft
- Adding ADA pathways from upland areas and to the waterfront, including a new accessible path to the water along the North Beach
- Installing a new ADA overwater platform to provide a stable surface where community members can enjoy activities on the water and "get their feet wet" at the plaza
- Enhancing shoreline ecological functions with habitat gravel, native vegetation, and lakebed cleanup
- Upgrading sewer, electrical, stormwater, and irrigation utilities as well as installing a new fire suppression system to serve the docks and Boiler Building
- Installing plaza improvements and amenities, including new surfacing, picnic tables/benches, signage, and the Mercer Island Medallions public art project
Construction is anticipated to begin in late summer or early fall. After a construction contract is awarded, the project is expected to take approximately 15 to 18 months to complete. Regular updates on project progress, schedule, and any anticipated park impacts will be shared on Let's Talk once construction begins.
Since 2022, the City has been coordinating with eight federal, state, and local agencies to secure more than 20 permits/approvals for this project, making this one of the most complex park redevelopment projects on Mercer Island in decades!
Thank you to the community for your patience as we worked to successfully permit this project.
This week, the City advertised the Luther Burbank Park Waterfront Improvements project for construction, marking a major step forward in completing renovations at the waterfront!
Design for this project began in 2020 and aims to provide universal access to the Luther Burbank waterfront by:
- Renovating/replacing the docks to better serve hand-powered and motorized watercraft
- Adding ADA pathways from upland areas and to the waterfront, including a new accessible path to the water along the North Beach
- Installing a new ADA overwater platform to provide a stable surface where community members can enjoy activities on the water and "get their feet wet" at the plaza
- Enhancing shoreline ecological functions with habitat gravel, native vegetation, and lakebed cleanup
- Upgrading sewer, electrical, stormwater, and irrigation utilities as well as installing a new fire suppression system to serve the docks and Boiler Building
- Installing plaza improvements and amenities, including new surfacing, picnic tables/benches, signage, and the Mercer Island Medallions public art project
Construction is anticipated to begin in late summer or early fall. After a construction contract is awarded, the project is expected to take approximately 15 to 18 months to complete. Regular updates on project progress, schedule, and any anticipated park impacts will be shared on Let's Talk once construction begins.
Since 2022, the City has been coordinating with eight federal, state, and local agencies to secure more than 20 permits/approvals for this project, making this one of the most complex park redevelopment projects on Mercer Island in decades!
Thank you to the community for your patience as we worked to successfully permit this project.
-
Boiler Building Construction Complete
Share Boiler Building Construction Complete on Facebook Share Boiler Building Construction Complete on X (formerly Twitter) Share Boiler Building Construction Complete on Linkedin Email Boiler Building Construction Complete link
The work on the Boiler Building and Annex is complete. The contractor is providing final documents. The contractor was not able to complete the sewer connection because the vault containing the sewer pump is leaking. It will be replaced when the waterfront renovation is constructed starting in Fall 2025. As part of the grant from Washington State Historical Society, new historical markers will be installed at this location and three other locations in the park. These markers will connect park users to a history of the park on the City's STQRY platform.
Phase 2 of the Boiler Building is planned for 2030. This will complete the renovation of the inside of the Boiler Building for expanded boating programs, including summer camps, classes and rentals. Additional ADA access and fire protection will be part of this phase.
The work on the Boiler Building and Annex is complete. The contractor is providing final documents. The contractor was not able to complete the sewer connection because the vault containing the sewer pump is leaking. It will be replaced when the waterfront renovation is constructed starting in Fall 2025. As part of the grant from Washington State Historical Society, new historical markers will be installed at this location and three other locations in the park. These markers will connect park users to a history of the park on the City's STQRY platform.
Phase 2 of the Boiler Building is planned for 2030. This will complete the renovation of the inside of the Boiler Building for expanded boating programs, including summer camps, classes and rentals. Additional ADA access and fire protection will be part of this phase.
-
Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete!
Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on Facebook Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on X (formerly Twitter) Share Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! on Linkedin Email Major Milestone Reached - Structural Reinforcement of the Building and Chimney Now Complete! link
On July 25, crews reached a major project milestone, completing the structural reinforcement of the building and chimney!
Other work on the project continued including:
- Reinstalling the parapet capstones along the perimeter of the roof.
- Painting the restrooms.
- Forming and pouring a new concrete countertop for the concession stand.
- Installing the new 400-amp power supply on the north wall of the building
- Installation of new plumbing fixtures.
- Installation of new outside light fixtures.
- Applying an anti-graffiti coating to the brick exterior.
Check out our photo library for pictures of the progress!
On July 25, crews reached a major project milestone, completing the structural reinforcement of the building and chimney!
Other work on the project continued including:
- Reinstalling the parapet capstones along the perimeter of the roof.
- Painting the restrooms.
- Forming and pouring a new concrete countertop for the concession stand.
- Installing the new 400-amp power supply on the north wall of the building
- Installation of new plumbing fixtures.
- Installation of new outside light fixtures.
- Applying an anti-graffiti coating to the brick exterior.
Check out our photo library for pictures of the progress!
-
Construction is Underway at the Boiler Building
Share Construction is Underway at the Boiler Building on Facebook Share Construction is Underway at the Boiler Building on X (formerly Twitter) Share Construction is Underway at the Boiler Building on Linkedin Email Construction is Underway at the Boiler Building link
Work has started on the Luther Burbank Boiler Building renovation project.
The last week of February, the City’s contractor, Ferguson Construction, took control of the site, clearing brush around the building, standing up safety fencing, disconnecting electrical service, and installing project signs. They’ve made progress on the inside of the building – preparing the inside structure for new flooring, updated restrooms, and importantly, a new roof and seismic retrofits to stabilize the brick building and chimney.
The first phase of this work requires a wide safety area around the building, including through the waterfront plaza area. During this period of work, pedestrian routes have been detoured. These detours will be in place throughout spring. The City’s contractor will reopen access through the waterfront as soon as it is safe to do so.
Check out photos of the work in our Boiler Building Renovation Photo Library. Updated regularly.
Construction updates www.mercerisland.gov/boilerbuilding
Work has started on the Luther Burbank Boiler Building renovation project.
The last week of February, the City’s contractor, Ferguson Construction, took control of the site, clearing brush around the building, standing up safety fencing, disconnecting electrical service, and installing project signs. They’ve made progress on the inside of the building – preparing the inside structure for new flooring, updated restrooms, and importantly, a new roof and seismic retrofits to stabilize the brick building and chimney.
The first phase of this work requires a wide safety area around the building, including through the waterfront plaza area. During this period of work, pedestrian routes have been detoured. These detours will be in place throughout spring. The City’s contractor will reopen access through the waterfront as soon as it is safe to do so.
Check out photos of the work in our Boiler Building Renovation Photo Library. Updated regularly.
Construction updates www.mercerisland.gov/boilerbuilding
-
Boiler Building Phase 1 Bid Awarded - Construction to Begin this Winter
Share Boiler Building Phase 1 Bid Awarded - Construction to Begin this Winter on Facebook Share Boiler Building Phase 1 Bid Awarded - Construction to Begin this Winter on X (formerly Twitter) Share Boiler Building Phase 1 Bid Awarded - Construction to Begin this Winter on Linkedin Email Boiler Building Phase 1 Bid Awarded - Construction to Begin this Winter link
At its January 2, 2024 regular meeting, the Mercer Island City Council awarded the bid proposal for Phase 1 of the Luther Burbank Boiler Building renovation project to Ferguson Construction (see AB 6380). The City Manager will now execute a contract with Ferguson and work will begin. The total cost of the contract is $2.5 million dollars.
What to Expect
As Phase 1 of the project moves forward, construction will begin in late winter this year and should be completed by the end of Q3* of this year. Here’s what park patrons should expect:
- Installation of a new roof and seismic retrofits to stabilize the brick building and chimney,
- Renovation of the boiler building restrooms, and
- Construction of a new rooftop deck on the annex.
The waterfront around the docks will remain open to the public but the area around the Boiler Building will be fenced off. There may be other restrictions to access periodically during construction.
Future phases of the renovation will finish the interior of the building and provide direct, convenient access from the parking lot to complete the building's transition to a waterfront activity center for small craft boating programs.
This Project is Made Possible By…
The City has received a $513,000 grant from the Washington State Historical Society and $343,000 in grant funding from the Washington State Recreation and Conservation Office which will help cover the cost of the renovations. Washington State taxpayers contributed to the design of this project through a Department of Commerce Grant.
*This is an estimated timeline. Public agencies, contractors, and suppliers continue to experience shortages of materials and long lead times on critical items, such as structural steel, plumbing, and building materials.
At its January 2, 2024 regular meeting, the Mercer Island City Council awarded the bid proposal for Phase 1 of the Luther Burbank Boiler Building renovation project to Ferguson Construction (see AB 6380). The City Manager will now execute a contract with Ferguson and work will begin. The total cost of the contract is $2.5 million dollars.
What to Expect
As Phase 1 of the project moves forward, construction will begin in late winter this year and should be completed by the end of Q3* of this year. Here’s what park patrons should expect:
- Installation of a new roof and seismic retrofits to stabilize the brick building and chimney,
- Renovation of the boiler building restrooms, and
- Construction of a new rooftop deck on the annex.
The waterfront around the docks will remain open to the public but the area around the Boiler Building will be fenced off. There may be other restrictions to access periodically during construction.
Future phases of the renovation will finish the interior of the building and provide direct, convenient access from the parking lot to complete the building's transition to a waterfront activity center for small craft boating programs.
This Project is Made Possible By…
The City has received a $513,000 grant from the Washington State Historical Society and $343,000 in grant funding from the Washington State Recreation and Conservation Office which will help cover the cost of the renovations. Washington State taxpayers contributed to the design of this project through a Department of Commerce Grant.
*This is an estimated timeline. Public agencies, contractors, and suppliers continue to experience shortages of materials and long lead times on critical items, such as structural steel, plumbing, and building materials.
-
Luther Burbank Boiler Building Bid Award
Share Luther Burbank Boiler Building Bid Award on Facebook Share Luther Burbank Boiler Building Bid Award on X (formerly Twitter) Share Luther Burbank Boiler Building Bid Award on Linkedin Email Luther Burbank Boiler Building Bid Award link
On January 2, 2024, the Mercer Island City Council will consider awarding the Luther Burbank Boiler Building Phase 1 project to Ferguson Construction (see AB 6380).
If approved, Phase 1 of the project would see the installation of a new roof and seismic retrofits to stabilize the 1928 brick building and chimney, as well as renovate the restrooms and construct a new rooftop deck on the annex.
The total cost of the contract is $2.5 million dollars. The City has received a $513,000 grant from the Washington State Historical Society and $343,000 in grant funding from the Washington State Recreation and Conservation Office which will help cover the cost of the renovations.
If the project is awarded, construction would begin in late winter 2024. The waterfront around the docks will be closed to the public periodically during construction.
A future phase of renovation will finish the interior of the building and provide direct, convenient access from the parking lot to complete the building's transition to a waterfront activity center for small craft boating programs. Washington State taxpayers contributed to the design of this project through a Department of Commerce Grant.
On January 2, 2024, the Mercer Island City Council will consider awarding the Luther Burbank Boiler Building Phase 1 project to Ferguson Construction (see AB 6380).
If approved, Phase 1 of the project would see the installation of a new roof and seismic retrofits to stabilize the 1928 brick building and chimney, as well as renovate the restrooms and construct a new rooftop deck on the annex.
The total cost of the contract is $2.5 million dollars. The City has received a $513,000 grant from the Washington State Historical Society and $343,000 in grant funding from the Washington State Recreation and Conservation Office which will help cover the cost of the renovations.
If the project is awarded, construction would begin in late winter 2024. The waterfront around the docks will be closed to the public periodically during construction.
A future phase of renovation will finish the interior of the building and provide direct, convenient access from the parking lot to complete the building's transition to a waterfront activity center for small craft boating programs. Washington State taxpayers contributed to the design of this project through a Department of Commerce Grant.
-
Mercer Island Arts Council Recommends Art Elements for Luther Burbank Waterfront
Share Mercer Island Arts Council Recommends Art Elements for Luther Burbank Waterfront on Facebook Share Mercer Island Arts Council Recommends Art Elements for Luther Burbank Waterfront on X (formerly Twitter) Share Mercer Island Arts Council Recommends Art Elements for Luther Burbank Waterfront on Linkedin Email Mercer Island Arts Council Recommends Art Elements for Luther Burbank Waterfront linkOn October 25, 2023, the Mercer Island Arts Council voted to recommend the plan for integrated public art elements for the Luther Burbank Park waterfront. The plan centers on the Mercer Island Medallions, 12 unique bronze pieces that highlight the natural and cultural history of Mercer Island, Luther Burbank Park, and the Lake Washington region. Artist Marsha Rollinger worked with City staff, the waterfront design team, and the Mercer Island community to design the medallions during summer 2023. Other coordinated elements include historic plaques and embellishments for the Boiler Building, the waterfront light pole, and a new informationalContinue reading
On October 25, 2023, the Mercer Island Arts Council voted to recommend the plan for integrated public art elements for the Luther Burbank Park waterfront. The plan centers on the Mercer Island Medallions, 12 unique bronze pieces that highlight the natural and cultural history of Mercer Island, Luther Burbank Park, and the Lake Washington region. Artist Marsha Rollinger worked with City staff, the waterfront design team, and the Mercer Island community to design the medallions during summer 2023. Other coordinated elements include historic plaques and embellishments for the Boiler Building, the waterfront light pole, and a new informational kiosk.
This public art project is funded by the City's 1% for Art in Public Places program and the Washington State Historical Society's Heritage Capital Project grant program. Rollinger was selected to develop the artwork following a competitive artist selection process that took place in early 2023.
The new art elements will be installed in 2025 at the end of construction of the waterfront renovation. Once installed, community members will be able to learn more about the project and individual pieces through STQRY, the City's digital engagement platform for public art. Learn more about Mercer Island's public art collection at www.mercerisland.gov/publicart.
-
Donate Waterfront Furnishings, Artwork and More...
Share Donate Waterfront Furnishings, Artwork and More... on Facebook Share Donate Waterfront Furnishings, Artwork and More... on X (formerly Twitter) Share Donate Waterfront Furnishings, Artwork and More... on Linkedin Email Donate Waterfront Furnishings, Artwork and More... link
Create a legacy at the waterfront! Opportunities to donate furnishings, artwork, and major site improvements are available this summer. Items include benches, tables, a drinking fountain, a kayak ramp, bronze medallions and a kiosk. Large site features such as a viewing deck, overwater platform and an elaborate terraced entrance to the waterfront are also offered. Scan the QR code to view items and make your donation today.

Donations will be accepted through the fall. Installation of donated items will occur in late 2024 or early 2025 during the completion construction. Inquiries should be directed to Paul West, Senior CIP Project Manager at 206-677-1028.
Create a legacy at the waterfront! Opportunities to donate furnishings, artwork, and major site improvements are available this summer. Items include benches, tables, a drinking fountain, a kayak ramp, bronze medallions and a kiosk. Large site features such as a viewing deck, overwater platform and an elaborate terraced entrance to the waterfront are also offered. Scan the QR code to view items and make your donation today.

Donations will be accepted through the fall. Installation of donated items will occur in late 2024 or early 2025 during the completion construction. Inquiries should be directed to Paul West, Senior CIP Project Manager at 206-677-1028.
-
Scoping and Contracting
Luther Burbank Dock and Waterfront Renovations has finished this stage -
Condition Assessment and Public Input
Luther Burbank Dock and Waterfront Renovations has finished this stage -
Concept Plan
Luther Burbank Dock and Waterfront Renovations has finished this stage -
30% Design
Luther Burbank Dock and Waterfront Renovations has finished this stage -
Secure Funding
Luther Burbank Dock and Waterfront Renovations has finished this stageFinalize grant funding and budgets to enable construction.
-
Final Design and Permitting
Luther Burbank Dock and Waterfront Renovations is currently at this stage- Local, State, and Federal permitting.
- Complete design based on permitting outcomes.
- Bid project and authorize bid award.
-
Construction
this is an upcoming stage for Luther Burbank Dock and Waterfront Renovations2026-2027
-
Integrated Art Elements for Luther Burbank Waterfront (16.4 MB) (pdf)
-
MI Medallions for Donation.pdf (2.93 MB) (pdf)
-
LB Dock and Waterfront 60% Design.pdf (25.5 MB) (pdf)
-
LBP Docks and Waterfront 30% Design.pdf (16.5 MB) (pdf)
-
Recommended Concept Design
-
Draft Preferred Concept
-
Open House 02September2020
-
LBDR Overview posters.pdf (11.2 MB) (pdf)
-
LBDR Alternative 1.pdf (6.78 MB) (pdf)
-
LBDR Alternative 2.pdf (6.73 MB) (pdf)
-
LBDR Alternative 3.pdf (7.35 MB) (pdf)
-
LBDR Alternatives Comparison Table.docx (17.1 KB) (docx)
-
LBDR_Open House Survey_print version.pdf (278 KB) (pdf)
-
LBDR Open House survey report.pdf (1.26 MB) (pdf)
-
-
Design Charrette 06August2020
-
LBDR Design Charrette_Summary and Notes.pdf (189 KB) (pdf)
-
LBDR Design Charrette Introduction Powerpoint (1.86 MB) (pdf)
-
LBDR Design Charrette Docks Powerpoint (1.03 MB) (pdf)
-
LBDR Design Charrette Breakwater Powerpoint (1000 KB) (pdf)
-
LBDR Design Charrette Access Powerpoint (1.08 MB) (pdf)
-
LBDR Design Charrette Placemaking Powerpoint (1.24 MB) (pdf)
-
LBDR design charrette saved chat.pdf (128 KB) (pdf)
-
LBDR Design Charrette polling results.pdf (144 KB) (pdf)
-
-
LBDR Public Involvement Plan draft 20210511.pdf (282 KB) (pdf)
-
Luther Burbank Dock Reconfiguration Demand Analysis 010219 (588 KB) (pdf)
-
2018 Survey Data - All Responses with Open Ended Questions (210 KB) (pdf)
-
Luther Burbank Dock and Adjacent Waterfront 30% Plans.pdf (11.9 MB) (pdf)
-
Phone 206-275-7864 Email sarah.bluvas@mercerisland.gov




