Construction Update for July 11
Here’s a look at construction progress at the Luther Burbank sport courts since the last update.
- FieldTurf finished installing the trench drain system on the east side of the courts.
- The conduit running the south fence line and the electrical handholes were installed.
- A few extra sections of the existing surface were removed, and NW Asphalt patched the saw cuts with new asphalt.
Now staff and DA Hogan, the City’s architect for this project, are completing inspections to confirm the courts are ready for the asphalt overlay. This project remains on schedule; view construction photos here.