Construction Update for November 7

Get your paddles ready! Beynon Sports finished installing the pickleball nets and court fencing this week, and staff are working on final details to open the facility for play this month.

Outstanding items include:

  • Completing the south hill – FieldTurf anticipates finishing the grading work this week and will secure it with plastic sheeting for the winter. The City’s Parks team will restore the hill with groundcover next spring.
  • Installing the new concrete access path from the parking lot – This item is weather-dependent, so the City may choose to open the courts before this item is finished.
  • Cleaning the courts – Beynon power-washed the courts this week, and they will be leaf-blown before FieldTurf demobilizes.
  • Placing rules signage – The City plans to use temporary signage through the winter and will modify the facility rules if necessary before permanent signage is installed in the spring.

View construction photos here.

Share Construction Update for November 7 on Facebook Share Construction Update for November 7 on Twitter Share Construction Update for November 7 on Linkedin Email Construction Update for November 7 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>