Construction Update for October 10
Investigation of court planarity continued this week. City staff, DA Hogan, FieldTurf, Northwest Asphalt, and Beynon, the subcontractor handling court surfacing, met on Tuesday to perform the string test and discuss options for correcting the asphalt ridges. Northwest Asphalt will also return later this week or early next week to paint test lines on the courts to assess the aesthetics of the ridges.
While a preferred paving correction is identified, FieldTurf continues to address other items, including:
- Finishing the new perforated drain on the south edge of the courts
- Regrading and rebuilding the existing gravel path from the restrooms to center court, which will connect to the new concrete sidewalk from the parking lot
View construction photos here.
This capital project has been completed. For updates about the Luther Burbank Park pickleball courts, visit www.mercerisland.gov/parksrec/page/luther-burbank-pickleball-courts.