Construction Update for October 24
Northwest Asphalt was able to take advantage of good weather this week and completed paving corrections, which was completed at no cost to the City and included:
- Removing layers of asphalt with a milling machine;
- Patching the northeast and southeast corners, where asphalt was removed down to the subgrade; and
- Overlaying the entire surface with a new layer of hot mix asphalt (HMA).
Today, City staff, DA Hogan, and FieldTurf conducted a new flood test to confirm court planarity. The test indicated that the new paving work was successful, so the last pieces of this construction phase can be completed. Next, Beynon Sports will install temporary striping, pickleball nets, and facility fencing, and FieldTurf will finish rebuilding the gravel path from the restrooms, grading the south hill, and installing the new concrete walkway from the parking lot.
Once these elements are done and DA Hogan and the City have inspected the work, the courts will open for play. View construction photos here.