Construction Update for April 10
This week, the contractor continued installing the new drainage system, including laying drainage pipe and placing a new catch basin within the play area. The project team from Berger and KPFF also conducted a site visit to observe the drainage work that has been completed to date. Drainage work and preparation for curbing will continue over the next couple of weeks. View construction photos here.