Roanoke Park Playground Replacement
Roanoke Park is a neighborhood park located at 70th Avenue SE and West Mercer Way. The park's playground equipment includes ship-themed climbing structures installed in 2004 as well as swings and a Spinami installed in 2012. All structures will be replaced as part of this playground replacement project, and the site will also be evaluated for ADA/accessibility upgrades as part of the process. Additionally, the Berger Partnership, the City's consultant leading design and community engagement for early playground replacements, is developing a site concept that will include improvements to parking and new perimeter fencing.
Construction of the playground renovation began in February 2025 and is expected to last 3-4 months. Follow along here on Let's Talk for weekly construction updates and photos!
Looking for general information about Mercer Island playground replacements? Find it here: www.mercerisland.gov/playgroundreplacements.
Roanoke Park is a neighborhood park located at 70th Avenue SE and West Mercer Way. The park's playground equipment includes ship-themed climbing structures installed in 2004 as well as swings and a Spinami installed in 2012. All structures will be replaced as part of this playground replacement project, and the site will also be evaluated for ADA/accessibility upgrades as part of the process. Additionally, the Berger Partnership, the City's consultant leading design and community engagement for early playground replacements, is developing a site concept that will include improvements to parking and new perimeter fencing.
Construction of the playground renovation began in February 2025 and is expected to last 3-4 months. Follow along here on Let's Talk for weekly construction updates and photos!
Looking for general information about Mercer Island playground replacements? Find it here: www.mercerisland.gov/playgroundreplacements.
-
Construction Update for May 8
Share Construction Update for May 8 on Facebook Share Construction Update for May 8 on Twitter Share Construction Update for May 8 on Linkedin Email Construction Update for May 8 linkThe contractor started forming the concrete curb that encloses the play area this week. Due to the constraints of the site, the concrete work has been broken out into two phases. Most of the curb will be poured in the next couple weeks. Then they will return to complete the curb and other concrete elements, including the picnic table pad, ADA parking stall, and new pathway from parking to the play area.
View construction photos here.
-
Construction Update for May 1
Share Construction Update for May 1 on Facebook Share Construction Update for May 1 on Twitter Share Construction Update for May 1 on Linkedin Email Construction Update for May 1 linkThis week, R&R Construction continued minor site work in preparation for concrete work to begin next week. More support posts for new play equipment have been installed, and the City's Stormwater team completed their work connecting the new play area drainage system to the existing outfall on 70th Ave SE.
View construction photos here.
-
Construction Update for April 24
Share Construction Update for April 24 on Facebook Share Construction Update for April 24 on Twitter Share Construction Update for April 24 on Linkedin Email Construction Update for April 24 linkThe new playground at Roanoke Park continues to take shape! Over the past two weeks, R&R Construction:
- Continued building the new drainage system
- Began installing the crushed rock subgrade for the accessible play area surfacing
- Removed more concrete footings leftover from previous playground equipment.
Posts for the new swings and spinner have also been installed, and the City’s Stormwater team built the pipe connection from the new play area drainage system to the existing stormwater outfall along 70th Ave SE.
Construction updates and photos are posted on Let’s Talk.
-
Construction Update for April 10
Share Construction Update for April 10 on Facebook Share Construction Update for April 10 on Twitter Share Construction Update for April 10 on Linkedin Email Construction Update for April 10 linkThis week, the contractor continued installing the new drainage system, including laying drainage pipe and placing a new catch basin within the play area. The project team from Berger and KPFF also conducted a site visit to observe the drainage work that has been completed to date. Drainage work and preparation for curbing will continue over the next couple of weeks. View construction photos here.
Construction updates will pause next week during spring break. Stay tuned for the next update on April 24!
-
Construction Update for April 3
Share Construction Update for April 3 on Facebook Share Construction Update for April 3 on Twitter Share Construction Update for April 3 on Linkedin Email Construction Update for April 3 linkThis week R&R Construction continued work to install the new drainage system, including trenching, placing drain fabric, and sourcing pipe and gravel backfill. Drainage work and preparation for curbing will continue over the next couple of weeks, then R&R Construction will start installing new play equipment footings.
View construction photos here.
-
Construction Update for March 27
Share Construction Update for March 27 on Facebook Share Construction Update for March 27 on Twitter Share Construction Update for March 27 on Linkedin Email Construction Update for March 27 linkDespite rainy weather this week, R&R Construction continued excavating soil to achieve the necessary grades for the renovated play area. Excavated material is currently stockpiled on site and will be used to soften the slope next to 70th Avenue SE at the end of the project. Next week, the contractor will continue work to prepare for installing the concrete curbing and drainage within the play area.
View construction photos here.
-
Construction Update for March 20
Share Construction Update for March 20 on Facebook Share Construction Update for March 20 on Twitter Share Construction Update for March 20 on Linkedin Email Construction Update for March 20 linkThis week, R&R Construction continued grading the site and began trenching for the new play area curbing. They will continue curbing work into next week, then progress to the drainage installation.
View construction photos here.
-
Construction Update for March 13
Share Construction Update for March 13 on Facebook Share Construction Update for March 13 on Twitter Share Construction Update for March 13 on Linkedin Email Construction Update for March 13 linkDespite the soggy weather this week, R&R Construction graded the site and marked the elevations needed to build up the new finished grade. Next, the contractor will continue grading the site and prepare for installing new play area curbing and drainage.
View construction photos here.
-
Construction Update for March 6
Share Construction Update for March 6 on Facebook Share Construction Update for March 6 on Twitter Share Construction Update for March 6 on Linkedin Email Construction Update for March 6 linkThe site was quiet this week while R&R Construction coordinates the additional site surveying work they need to complete. Staff anticipate the crew will return next week to start grading the site in preparation for installing the play area curbing and new drainage system.
-
Construction Update for February 27
Share Construction Update for February 27 on Facebook Share Construction Update for February 27 on Twitter Share Construction Update for February 27 on Linkedin Email Construction Update for February 27 linkR&R Construction completed demolition of the site this week. Next, they will complete additional surveying work to confirm grades before starting other site work, such as preparing to install the new play area curbing and drainage system.
View construction photos here.
Project Timeline
-
Project Initiation
Roanoke Park Playground Replacement has finished this stage- Site assessment
- Playground equipment + vendor research
- ADA upgrades evaluation
- Draft concepts
-
Community Survey
Roanoke Park Playground Replacement has finished this stageOpen December 20, 2023, to January 12, 2024
View draft layout options that will work at the site and provide input on your playground equipment likes and dislikes.
-
Virtual Public Meeting
Roanoke Park Playground Replacement has finished this stageJanuary 30, 2023 | 6pm | Register here
See the latest layout options based on the results of the community survey and share more input about equipment selection and layout.
Couldn't make the meeting? Share additional input on swings and site amenities through February 9 here. Responses will be combined with those received during the meeting to inform the final site plan and equipment selection.
-
Finalize Design, Order Equipment and Secure Permits
Roanoke Park Playground Replacement has finished this stage -
Playground Under Construction
Roanoke Park Playground Replacement is currently at this stage2025
-
Project Complete
this is an upcoming stage for Roanoke Park Playground Replacement
Construction Progress
Q&A from Virtual Public Meeting on 01.30.24
- Heights are an important element of playgrounds. How does the proposed “exciting heights” 5-12 climbing structure compare to the existing playground height?
- Roanoke Park is currently known as the “Pirate Ship” park. Is it possible to maintain this theme or bring in another exciting theme?
- Is the soft surface going to be similar to the surface used at the Mercerdale Park playground?
- For all Mercer Island playgrounds: Are they all designed for all ages, or are some playgrounds designed specifically for 2 to 5-year-olds and others specifically for older kids?
Who's Listening
-
Phone 206-275-7864 Email sarah.bluvas@mercerisland.gov