The Roanoke Park Playground site has been busy! This week, the contractor:

  • Finished the first section of concrete curbing
  • Installed equipment footings for the new 2-5 play structure
  • Completed trenching and compaction for the remaining curb section
  • Started shaping the stormwater swale on the west perimeter of the play area
  • Laid some of the base rock that for the new poured-in-place accessible play surfacing

The remaining curb section is scheduled to be poured next week (weather permitting). View construction photos here.