Updates for June 2024
Design and coordination continue to replace aging equipment and make site improvements at Roanoke Park. This post provides an update on work completed to-date.
Permitting
In mid-March, staff and the design team met with Permitting and confirmed that this capital project will require additional geotechnical assessment and a Critical Areas Review 1. Additionally, the design team adjusted the site layout and ADA parking space location to avoid potential tree impacts from grading and other site work during construction. Permit applications were submitted on June 4, with an anticipated review time of 6-10 weeks.
Ordering Play Equipment
New play equipment is being provided by two play manufacturers:
- Landscape Structures Inc.: 2-5 Play Structure, Swings
- Berliner: 5-12 Net Climber, Cone Spinner
Staff ordered the play equipment in April, and delivery is anticipated in late summer. Like in other industries, both play manufacturers are experiencing production and shipping delays, resulting in long lead times for play equipment delivery. The design team maintains regular contact with both manufacturers and updates the City as delivery timelines improve.
Construction Timing
The City plans to contract with Allplay Systems, a Northwest-based playground provider, to install new play equipment and complete site improvements, which include accessible playground surfacing and a new ADA parking space. Allplay is finalizing the proposed scope of work now, and staff anticipate completing contracting needs this summer. Based on permitting and equipment delivery timelines, construction likely will not begin until September. The playground will remain open until the project is ready to break ground.
Another project update will be posted once permits are approved. In the meantime, contact Sarah Bluvas, CIP Project Manager, at sarah.bluvas@mercerisland.gov with project questions.