Construction Update April 23, 2025
This week, OMA Construction crews continued to haul and place new aggregate for base under the new parking lot and topsoil for landscaped areas. Also this week, the existing fire hydrant was removed, and a new one will be installed. Next week, concrete crews plan to form and pour the new concrete sidewalks on the site. Asphalt crews are currently scheduled for the week of May 5th to pave the first lift of asphalt.