Construction Update May 12, 2025

Last week, asphalt crews paved the first lift of hot mix asphalt for the new parking lot. Also, more topsoil was placed and landscaping crews began installing the new irrigation system. This week, electrical crews will pour new light bases along the north side of the parking lot and asphalt crews are scheduled to return to pave the final top lift of asphalt.