Construction Update May 5, 2025

Last week, OMA Construction concrete crews formed and poured all the new concrete sidewalk within the parking facility and along SE 27th Street, and also completed grading and prepping the parking area for asphalt paving. This week, asphalt crews will place the bottom lift of hot mix asphalt paving on the site.