November 13, 2026 Construction Update

This week Kar-Vel Construction completed the first of three new watermain connections. This connects the new 10” watermain on Gallagher Hill Road to the existing 12” watermain on SE 40th Street. Next week crews will begin installing the new pressure reducing valve vault at the bottom of Gallagher Hill Road. Following the vault installation new water services and fire hydrants will be installed. This new 10” waterline will replace the existing asbestos cement waterline before installation of the new 24” supply line.