Water Supply Line Project Update to City Council
At the October 21, 2025 City Council meeting, the Council received an update on the Water Supply Pipeline project. Design work by RH2 and construction coordination by Scarsella Brothers Inc has continued and has reached the 60% stage milestone.
The new pipe alignments, general footprint of the project, and roadway improvements are identified. Initial cost estimates have also been completed. While there are some remaining scope elements to be defined, the project is moving towards construction in Q1 2026.
This project has two primary phases: water and roadway. The underground and water work will occur first, starting in March 2026 and this is anticipated to last 10 to 12 months. Roadway improvements will follow, beginning in early spring 2027 and are estimated to take approximately 8 months to construct. Substantial completion of the project is expected by the end of 2027.