Luther Burbank Park Sport Courts Renovation

Share Luther Burbank Park Sport Courts Renovation on Facebook Share Luther Burbank Park Sport Courts Renovation on Twitter Share Luther Burbank Park Sport Courts Renovation on Linkedin Email Luther Burbank Park Sport Courts Renovation link

This capital project has been completed. For updates about the Luther Burbank Park pickleball courts, visit www.mercerisland.gov/parksrec/page/luther-burbank-pickleball-courts.

An outdoor sports court facility featuring eight pickleball courts

The tennis courts at Luther Burbank Park were constructed in 1972 below grade and on top of a dense silt/clay subgrade. The subgrade has settled over the last 50 years, and the court surface has become wavy, affecting recreational play. Tree root intrusions also created extensive cracking in the asphalt surface, which was fixed with temporary patching in 2018.

The 2022 PROS Plan identified the Luther Burbank courts as a preferred location for pickleball court design, and a capital project to renovate the courts was included in the 2023-2024 Biennial Budget and Capital Improvement Program. The City also received grant funding through the King County Parks Capital and Open Space program to support this capital.

Construction started in May 2024 and included removing the existing subgrade and asphalt; paving new asphalt; and installing temporary court markings, new pickleball nets, and facility fencing. FieldTurf, the City's contractor for this project, returned in 2025 to install permanent acrylic court surfacing and finish other items. The courts are now complete and open on a first-come, first-served basis. Facility rules are posted on-site and on the City website.

The tennis courts at Luther Burbank Park were constructed in 1972 below grade and on top of a dense silt/clay subgrade. The subgrade has settled over the last 50 years, and the court surface has become wavy, affecting recreational play. Tree root intrusions also created extensive cracking in the asphalt surface, which was fixed with temporary patching in 2018.

The 2022 PROS Plan identified the Luther Burbank courts as a preferred location for pickleball court design, and a capital project to renovate the courts was included in the 2023-2024 Biennial Budget and Capital Improvement Program. The City also received grant funding through the King County Parks Capital and Open Space program to support this capital.

Construction started in May 2024 and included removing the existing subgrade and asphalt; paving new asphalt; and installing temporary court markings, new pickleball nets, and facility fencing. FieldTurf, the City's contractor for this project, returned in 2025 to install permanent acrylic court surfacing and finish other items. The courts are now complete and open on a first-come, first-served basis. Facility rules are posted on-site and on the City website.

This capital project has been completed. For updates about the Luther Burbank Park pickleball courts, visit www.mercerisland.gov/parksrec/page/luther-burbank-pickleball-courts.

  • Construction Update for October 3

    Share Construction Update for October 3 on Facebook Share Construction Update for October 3 on Twitter Share Construction Update for October 3 on Linkedin Email Construction Update for October 3 link
    supporting image

    Earlier this week, Northwest Asphalt placed the second pavement lift, and the project team conducted the flood test to check court drainage and planarity. Drainage performed as planned, but more testing is necessary to confirm court planarity.

    During the flood test, the team found a few high ridges along the paving seams. Finding ridges is common for sport court paving, and there are options for correcting the ridges before the acrylic surfacing is installed in spring 2025. Next week, the team will conduct a string test, which involves pulling a string across the north/south length of the courts and walking it east/west to observe where the slope may be high or low. After the string test, staff, DA Hogan, and the construction team will identify the best correction plan.

    As a reminder, the courts need to cure for a few weeks before new pickleball nets and temporary striping are installed. While the courts cure, FieldTurf will complete other items, including finishing the new perforated drain on the south edge, building the new access path, and grading the south hillside. Additionally, the contractor will make improvements to the existing gravel path that leads from the play area restrooms to the courts.

    This project remains on track, and the courts are still anticipated to open for play later this month. View construction photos here.

  • Construction Update for September 26

    Share Construction Update for September 26 on Facebook Share Construction Update for September 26 on Twitter Share Construction Update for September 26 on Linkedin Email Construction Update for September 26 link
    supporting image

    Northwest Asphalt completed the first lift of paving on Tuesday and will return soon to correct some high and low spots, which is typical for asphalt work. Staff anticipate the second lift and flood test to confirm planarity will be completed next week. Then the new pavement will cure for a couple weeks while FieldTurf turns back to other items, including:

    • Finishing the new drain pipe on the south border;
    • Installing new court fencing; and
    • Starting the finishing work for the south hill and new access path.


    This project remains on track, and the courts are still anticipated to open for play in October. View construction photos here.

  • Construction Update for September 19

    Share Construction Update for September 19 on Facebook Share Construction Update for September 19 on Twitter Share Construction Update for September 19 on Linkedin Email Construction Update for September 19 link
    supporting image

    Here’s a look at progress since last week and upcoming construction activities.


    Subgrade Remediation

    Excavation of the existing subgrade is complete, and City staff anticipate all new subgrade material will be placed by early next week.

    On Monday, the project team proof-rolled the base aggregate layer to ensure it will be strong enough to pave. A super solo dump truck hauling 10 yards of pea gravel and weighing approximately 35 tons total drove back and forth across the base while AESI assessed the impact. Only one small area needed to be strengthened after the proof roll, which is good news for the remediation work. DA Hogan inspected the base subgrade on Tuesday and approved moving forward with finishing the subgrade remediation.

    Now FieldTurf is placing the final layers of rock material, which DA Hogan will inspect early next week.


    New Perforated Drain Pipe for South Edge

    As part of the new scope of work, FieldTurf is replacing an old drain pipe installed on the south border of the facility. The new pipe will catch groundwater draining off the hillside and help the Parks Operations team maintain the courts.


    Upcoming Work: Paving and Planarity Test

    Once the top subgrade layer is inspected and approved by DA Hogan, the project will move onto paving. Northwest Asphalt, the subcontractor handling paving, will install asphalt in two lifts. Following paving, the project team will conduct a flood test to confirm the planarity, or relative smoothness, of the court surface to ensure the asphalt install is consistent.

    The best method for confirming court planarity is to conduct a flood test, which involves flooding the courts with 1” to 2” of water, then observing how the water drains/evaporates. If water pools in any areas, those areas are uneven and may be adjusted before construction is complete. This is a critical quality control step to ensure that the courts are constructed correctly and to avoid major repair or reconstruction needs in the future.



    This project remains on track, and the courts are still anticipated to open for play in October. View construction photos here.


  • Construction Update for September 12

    Share Construction Update for September 12 on Facebook Share Construction Update for September 12 on Twitter Share Construction Update for September 12 on Linkedin Email Construction Update for September 12 link
    supporting image

    Excavation of the existing subgrade continued this week. FieldTurf is removing old material in sections, then backfilling with new crushed rock to build the stronger base for paving. As the contractor works from east to west, we are seeing the excavation depth to reach strong soils decrease, which City staff anticipated based on the subgrade tests performed by AESI in July. Subgrade remediation will continue through next week, weather-permitting.


    This project is back on track, and the courts are currently planned to reopen for play in October. View construction photos here.


  • Construction Update for September 5

    Share Construction Update for September 5 on Facebook Share Construction Update for September 5 on Twitter Share Construction Update for September 5 on Linkedin Email Construction Update for September 5 link
    supporting image

    On Tuesday, September 3, the City Council authorized a budget appropriation to remediate the failing subgrade and complete the Luther Burbank Park Sport Courts Renovation. (AB 6533)

    FieldTurf, the City’s contractor, has resumed construction, starting with removing and disposing of the existing asphalt. After removing the asphalt, FieldTurf began excavating the subgrade under the consultation of AESI, the City's geotechnical consultant. AESI is monitoring excavation to ensure the contractor only removes as much weak material as necessary to reach stronger soils. Once excavation is complete, new material will be laid and compacted to create a stronger base for asphalt paving.

    This project is back on track, and the courts are currently planned to reopen for play in October. View construction photos here.

  • City Council Reviews Construction Changes on September 3

    Share City Council Reviews Construction Changes on September 3 on Facebook Share City Council Reviews Construction Changes on September 3 on Twitter Share City Council Reviews Construction Changes on September 3 on Linkedin Email City Council Reviews Construction Changes on September 3 link

    Construction of the Luther Burbank Park Sport Courts Renovation remains suspended while the City works with the designer and contractor to finalize the scope of work to repair the failing subgrade prior to repaving the courts. The proposed change order is significant, so staff plan to return to City Council on September 3 to seek authorization and a budget appropriation to move forward with the work. Staff anticipate construction will resume by early September.

    Details for joining the City Council meeting are available below.

    The hybrid meeting will be live streamed on the City Council’s YouTube Channel beginning at 5pm.

    Register to Speak: Individuals wishing to speak live during Appearances (public comment period) must register with the City Clerk at 206.275.7793 or cityclerk@mercerisland.gov before 4pm on September 3, 2024. Each speaker will be allowed three (3) minutes to speak. A timer will be visible to online speakers, City Council, and meeting participants.


    Join by Telephone at 5pm: To listen to the meeting via telephone, please call 253.215.8782 and enter Webinar ID 878 1912 3930, Password 730224 when prompted.


    Join by Internet at 5pm: To watch the meeting online via your computer, follow these steps:

    1. Click this link (Webinar ID 8878 1912 3930; Password 730224)
    2. If the Zoom app is not installed on your computer, you will be prompted to download it.
    3. If prompted, enter Webinar ID 878 1912 3930, Password 730224.


    Join In-Person at the Mercer Island Community & Event Center at 5pm: The meeting will take place in the Slater Room Council Chambers, 8236 SE 24th Street.

  • Construction Delayed Due to Failing Subgrade

    Share Construction Delayed Due to Failing Subgrade on Facebook Share Construction Delayed Due to Failing Subgrade on Twitter Share Construction Delayed Due to Failing Subgrade on Linkedin Email Construction Delayed Due to Failing Subgrade link

    Based on the testing results from last week, it has been determined that the failing subgrade must be replaced before court paving can be completed. This additional work requires a change order for the construction contract and includes:

    • Removing more of the old asphalt surface;
    • Removing weak soils from the subgrade; and
    • Building a stronger base with new material.

    Preparations for paving the courts will resume after the base is repaired. While this project was ahead of schedule earlier this month, the construction pause and the scope of the subgrade remediation unfortunately delay completion. Staff now anticipate opening the courts by early October. User groups have been notified that the facility will not be available for play in August as originally planned.

    Staff are still finalizing the change order with DA Hogan and FieldTurf. The new project timeline and regular updates will be posted on Let’s Talk once construction can restart.

  • Construction Update for July 18

    Share Construction Update for July 18 on Facebook Share Construction Update for July 18 on Twitter Share Construction Update for July 18 on Linkedin Email Construction Update for July 18 link
    supporting image

    While prepping the sport courts for the asphalt overlay last week, City staff and the contractor discovered that the subgrade, or soil that the existing pavement is built on, is failing in some areas. Construction has paused so Associated Earth Sciences Inc. (AESI) could perform subgrade testing and provide recommendations for remediation.

    This week, AESI used a dynamic cone penetrometer, or DCP, to test soil strength in five areas on the courts. A DCP device consists of a steel rod, a hardened conical tip, and a standard weight hammer. During testing, the hammer is raised to the top of the rod and dropped to drive the rod into the ground. The DCP of the soil is recorded after each blow of the hammer and correlated to standard measures of soil strength. After identifying the DCP measurement, the consultant used a t-handle probe to confirm the depth to firm soils.

    Once the soil test results and remediation recommendations are received, City staff, DA Hogan, and FieldTurf will evaluate the project design and adjust as needed to strengthen the subgrade.




  • Construction Update for July 11

    Share Construction Update for July 11 on Facebook Share Construction Update for July 11 on Twitter Share Construction Update for July 11 on Linkedin Email Construction Update for July 11 link
    supporting image

    Here’s a look at construction progress at the Luther Burbank sport courts since the last update.

    • FieldTurf finished installing the trench drain system on the east side of the courts.
    • The conduit running the south fence line and the electrical handholes were installed.
    • A few extra sections of the existing surface were removed, and NW Asphalt patched the saw cuts with new asphalt.


    Now staff and DA Hogan, the City’s architect for this project, are completing inspections to confirm the courts are ready for the asphalt overlay. This project remains on schedule; view construction photos here.


  • Construction Update for June 27

    Share Construction Update for June 27 on Facebook Share Construction Update for June 27 on Twitter Share Construction Update for June 27 on Linkedin Email Construction Update for June 27 link
    supporting image

    The contractor began installing the new trench drain system on the east side of the courts this week. After installation is complete, the courts will be cleaned and prepped for paving. That phase includes installing new asphalt in the sawcut areas, then overlaying the entire court area with new asphalt.


    There will be no Let’s Talk update next week due to the Fourth of July holiday. The next update will be posted on Thursday, July 11.


    This project remains on schedule; view construction photos here.