Mercerdale Playground Renovation Project
Consultation has concluded
Mercerdale Park playground ("Train Park") is now open! Note that crews will be finishing the final touches over the next few weeks, but the playground is available for use.
Playground Completion is Delayed until Spring
The Mercerdale Park playground equipment installation is delayed again. Continuing record cold weather has slowed site work and prevents us from installing the new playground surfacing until the weather cooperates. Dry weather and nighttime low temps that stay consistently above 45 degrees are key to the success of the rubber surfacing.
Last fall, manufacturing and supply chain issues delayed the arrival of equipment. Playworld, theContinue reading
Mercerdale Park playground ("Train Park") is now open! Note that crews will be finishing the final touches over the next few weeks, but the playground is available for use.
Playground Completion is Delayed until Spring
The Mercerdale Park playground equipment installation is delayed again. Continuing record cold weather has slowed site work and prevents us from installing the new playground surfacing until the weather cooperates. Dry weather and nighttime low temps that stay consistently above 45 degrees are key to the success of the rubber surfacing.
Last fall, manufacturing and supply chain issues delayed the arrival of equipment. Playworld, the manufacturer of the playground equipment, experienced a significant fire at their plant in early May. News story here. We received equipment in December, and our equipment is now installed.
Our partner, Mercer Island Preschool Association supported this project from the beginning. MIPA has contributed and raised over $54,000 for the project. Way to go MIPA!
Why is the City Replacing the Playground Equipment?
The existing playground is 19 years old, and the equipment is at the end of its useful life. The groundcover chips have also broken down and are clogging the drainage system. The level of the play surface will be raised to meet the top of the existing concrete edging to improve accessibility, but the edging, seating and landscaping will remain in place.
-
Join us on July 9 for a Ribbon-Cutting Event
Share Join us on July 9 for a Ribbon-Cutting Event on Facebook Share Join us on July 9 for a Ribbon-Cutting Event on Twitter Share Join us on July 9 for a Ribbon-Cutting Event on Linkedin Email Join us on July 9 for a Ribbon-Cutting Event linkYou are invited to join us for a ribbon-cutting ceremony to celebrate the culmination of this community-driven project and the re-opening of a beloved play space. The ribbon-cutting ceremony is also the kick-off to Summer Celebration festivities!
We hope to see you Saturday, July 9 at 11 AM!
All are welcome!
-
Mercerdale Playground is Now Open
Share Mercerdale Playground is Now Open on Facebook Share Mercerdale Playground is Now Open on Twitter Share Mercerdale Playground is Now Open on Linkedin Email Mercerdale Playground is Now Open linkAfter months of delays due to supply chain issues, extended wet weather, and more, the Mercerdale Playground is ready for action. City crews officially opened the park to the public on June 27, 2022.
Islanders are welcome to utilize the playground starting opening day. City crews will be finishing several final touches over the next few weeks, but the playground is ready for action.
We hope you enjoy this new resource for the young Islanders in your lives.
-
Mercerdale Playground June 21 Update
Share Mercerdale Playground June 21 Update on Facebook Share Mercerdale Playground June 21 Update on Twitter Share Mercerdale Playground June 21 Update on Linkedin Email Mercerdale Playground June 21 Update linkSo close!
Crews installed the poured in place playground surfacing on Thursday evening and worked on the train tracks through the weekend.
With this stint of dry weather, we’re anticipating the playground should open very soon!
Visit the photo gallery to see the latest progress.
-
Play Area Surface Installation Continuing this Week
Share Play Area Surface Installation Continuing this Week on Facebook Share Play Area Surface Installation Continuing this Week on Twitter Share Play Area Surface Installation Continuing this Week on Linkedin Email Play Area Surface Installation Continuing this Week linkThe City is working with Northwest Playground to finish the Mercerdale Park playground replacement project. The installation of the playground surfacing has been challenging due to a very wet spring.
The Northwest Playground team is switching to a different binder that will allow them to install the rubberized surfacing even in slightly drizzly weather. Tuesday and Wednesday’s dry weather will allow the base layer to dry out so that the surface can go in on Thursday when we have a dry day forecasted.
The signature train tracks will be cut into the surface on Friday and installed on Saturday when it is expected to be dry again. Next week, the team will seam the play grass to the rubberized surface and clean up the site.
-
Play Grass Installed Under the Climber
Share Play Grass Installed Under the Climber on Facebook Share Play Grass Installed Under the Climber on Twitter Share Play Grass Installed Under the Climber on Linkedin Email Play Grass Installed Under the Climber linkLast week, the surfacing crew installed play grass under the climbing structure at the playground. The grass mat was laid over the top of four inches of foam cushioning for safety. The crew is waiting to finish the poured-in-place rubber surfacing which continues to be delayed by unpredictable wet weather. The crew just needs four dry days to get the work done. That has been a challenge this very wet spring. We know that many kids and their parents are eager to have the fence come down! Not much longer and the playground will be open.
-
Rubber Surfacing has Arrived!
Share Rubber Surfacing has Arrived! on Facebook Share Rubber Surfacing has Arrived! on Twitter Share Rubber Surfacing has Arrived! on Linkedin Email Rubber Surfacing has Arrived! linkThe playground surface crew is working to install the poured-in-place resilient rubber surfacing this week and next week. The weather is expected to cooperate. First a thick layer of shredded rubber is installed over the gravel base. Then the top color layer is applied to make a smooth finished surface. The binder takes 2-3 days to dry. After that, play grass will be installed under the main climbing structure. That work should be completed by the end of May.
The last phase of the playground installation will start in early June. The contractor will clean up the site and inspect the play equipment to make sure it is working properly. City crews will install benches and finish landscaping in preparation for opening the playground later in June.
-
Concrete Flatwork
Share Concrete Flatwork on Facebook Share Concrete Flatwork on Twitter Share Concrete Flatwork on Linkedin Email Concrete Flatwork linkUpdate: Concrete pathways around the playground are being poured and setting!
- - - - - - - - - -
Due to the ongoing King County concrete strike, the City’s contractor has coordinated with an out of county concrete supplier to complete the concrete flatwork around the playground. The demand for this work is high, but crews have scheduled the concrete flatwork for April 19.
Playground experts are still watching for the perfect succession of dry, warm days and moderate temperatures at night (for curing purposes) to install the resilient rubber playground surfacing. While the weather has gotten close a few times this spring, installation experts felt the conditions were not quite right. Once the playground surfacing is in place, crews will then install the playground grass. Crews will need one week onsite after the resilient rubber surfacing is completed to finish.
Crews continue to prepare for the opening of the playground, including installing the park bench plaques that have just arrived!
Updated April 14, 2022
-
Ready for Surfacing and Concrete!
Share Ready for Surfacing and Concrete! on Facebook Share Ready for Surfacing and Concrete! on Twitter Share Ready for Surfacing and Concrete! on Linkedin Email Ready for Surfacing and Concrete! linkThe play equipment is installed! The playground is close to completion but two final steps remain before the playground can re-open: (1) play surface installation and (2) concrete flatwork.
Installation of the resilient rubber surfacing (like Luther Burbank Park playground) needs warmer weather. While crews have been waiting on the weather to cooperate, the project also faces a possible delay with the ongoing concrete strike.
There are paths and bench pads that require large amounts of concrete. The strike has lasted for three months, longer than City staff expected. Unfortunately, the playground cannot reopen until this work is also completed.
In the meantime, the installation team will work to complete other details so that reopening can occur quickly once the strike is resolved.
-
Playground Equipment Installed
Share Playground Equipment Installed on Facebook Share Playground Equipment Installed on Twitter Share Playground Equipment Installed on Linkedin Email Playground Equipment Installed linkCrews have been installing the new playground equipment! The structures were completed the first week of February. Check out the photos here.
The playground surfacing crew needs dry weather and 45-degree temperatures to install the resilient surfacing – it may take several weeks to get a window.
City staff are estimating completion in late February.
-
Playground Installation Update
Share Playground Installation Update on Facebook Share Playground Installation Update on Twitter Share Playground Installation Update on Linkedin Email Playground Installation Update linkIn mid-December, crews finished installing the train play sculpture and the rest of the playground structures are being installed!
Unfortunately, the holidays, snow, and cold weather shut down operations for the past two weeks.
Next steps: Crews have two more weeks of assembly to finish the play structures and the playground surfacing crew needs dry weather and 50-degree temperatures to install the resilient surfacing – it may take several weeks to get a window.
City staff are estimating completion in late February.
Project Timeline
-
Project Initiation
Mercerdale Playground Renovation Project has finished this stage -
Public Meeting #1
Mercerdale Playground Renovation Project has finished this stageFebruary 8, 2021 Virtual Public Meeting
Let's Talk project page opens in March to collect written feedback
-
Public Meeting #2
Mercerdale Playground Renovation Project has finished this stageApril 14, 2021 Virtual Public Meeting
See the latest layout options, colors and selections of equipment. Ask questions and give us your input.
-
Parks and Recreation Commission Meeting
Mercerdale Playground Renovation Project has finished this stage -
City Council approval
Mercerdale Playground Renovation Project has finished this stageMay 18, 2021 City Council Virtual Meeting - view meeting video footage here.
-
Playground Under Construction
Mercerdale Playground Renovation Project has finished this stageSummer-Fall 2021
-
Project Complete
Mercerdale Playground Renovation Project is currently at this stageWinter 2022
Project Photos
Documents Library
- Inclusive Playground Rating for Current Options.pdf (822 KB) (pdf)
- Equipment and Layout Options.pdf (22 MB) (pdf)
- Mercerdale Playground April 14 Presentation.pdf (14.4 MB) (pdf)
- Public Meeting #2 Survey results.docx (95.7 KB) (docx)
- April 14 Mercerdale Meeting QA Report.pdf (69.2 KB) (pdf)
- Designs
- Mercerdale Playground Presentation meeting #1.pdf (8.43 MB) (pdf)
FAQs
- Why is the playground closed? Will it reopen soon?
- Is the new playground going to be bigger?
- Will there be a train in the new playground?
- Why are you proposing a rubber play surface? Isn't that toxic to children?
- Is the color scheme in the pictures what is going to be built?
- My kids love this playground. How can I help?