Construction Progress

Sawcutting concrete patches
previous next
FieldTurf sawcut concrete patches that were installed during previous court repairs. The patches will be removed before the entire facility is paved with a new asphalt overlay.
Restored mural
Completed court surfacing
Applying acrylic surfacing
Prepping the courts for permanent surfacing and striping
Replanting the south hill
New handrailing for the gravel path
Courts are open for play!
Reduced construction zone
New concrete sidewalk
New nets and fences
New perimeter fence
Pouring concrete for net post footings
Coring foundation holes for pickleball net and fence posts
Installing temporary court markings
Confirming court planarity
Conducting a second flood test
Paving the new asphalt overlay
Paving the new asphalt overlay
Paving the new asphalt overlay
New asphalt patches
Completing the new asphalt overlay
Making paving corrections
Making paving corrections
Making paving corrections
Making paving corrections
Refreshing the existing gravel path
String test to investigate planarity
Confirming court drainage
Conducting a flood test
Completed asphalt paving
Asphalt paving on 09.24.24
Asphalt paving on 09.30.24
Asphalt paving on 09.30.24
Asphalt paving on 09.30.24
Asphalt paving on 09.24.24
Asphalt paving on 09.24.24
Asphalt paving on 09.24.24
Subgrade remediation progress 09.18.24
Proof-rolling the base aggregate
Trenching for a new drain pipe on the south edge
Compacting crushed rock subgrade
Monitoring excavation and backfill
Subgrade remediation progress 09.13.24
New crushed rock subgrade in northwest quadrant
Testing subgrade after excavation
Compacting new crushed rock
Placing new crushed rock subgrade
Marking sections for grading
Excavating weak subgrade
Removing existing asphalt
Removing existing asphalt
Patching sawcut sections with new asphalt
Patching sawcut sections with new asphalt
Concrete setting for ACO trench drain system
Pouring concrete for trench drain system
Installing trench drain system
New ACO trench drain system
Investigating stormwater infrastructure
Installing conduit
Backfilling electrical trenches
Construction progress 06.13.24
Excavating the south hill
Removing tennis net posts
Removing sawcut asphalt
Construction access road
Site visit on 06.12.24
Excavating the south hill
Removing sawcut asphalt
Sawcutting concrete patches
Sawcutting around the perimeter
Fence removal
Construction signage