On September 16, the project team proof-rolled the base aggregate layer to ensure it will be strong enough to pave. A super solo dump truck hauling 10 yards of pea gravel and weighing approximately 35 tons total drove back and forth across the base while AESI assessed the impact. Only one small area needed to be strengthened after the proof roll, which is good news for the remediation work.